A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the method used to select engineers and general |
|
contractors for certain state highway construction projects. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Chapter 223, Transportation Code, is amended by |
|
adding Subchapter G to read as follows: |
|
SUBCHAPTER G. CONSTRUCTION MANAGER-GENERAL CONTRACTOR METHOD |
|
Sec. 223.301. DEFINITION. In this subchapter, |
|
"construction manager-general contractor method" means a delivery |
|
method by which the department contracts with an engineer for |
|
design and construction phase services and contracts separately |
|
with a construction manager to serve as the general contractor and |
|
to provide consultation during the design and construction of a |
|
state highway. |
|
Sec. 223.302. USE OF CONSTRUCTION MANAGER-GENERAL |
|
CONTRACTOR METHOD. Notwithstanding any other law requiring a |
|
particular procurement procedure, including Subchapter A of this |
|
chapter, the department may use the construction manager-general |
|
contractor method to select a general contractor for a state |
|
highway project as provided by this subchapter. |
|
Sec. 223.303. CONSTRUCTION MANAGER. (a) For purposes of |
|
this subchapter, a construction manager may be a sole |
|
proprietorship, partnership, corporation, or other legal entity. |
|
(b) A construction manager serves as the general contractor |
|
for a state highway project and assumes the risk for the |
|
construction of the state highway at the contracted price. |
|
(c) A construction manager shall provide consultation to |
|
the department regarding construction of a state highway project |
|
during and after the design of the project, including consultation |
|
regarding preconstruction services such as scheduling, pricing, |
|
phasing, technical innovations, site investigation, and risk |
|
mitigation. |
|
(d) The contracted price may be a guaranteed maximum price |
|
or converted to a lump sum. |
|
Sec. 223.304. USE OF ENGINEER. (a) On or before the |
|
selection of a construction manager, the department shall select an |
|
engineer to prepare the construction documents for the state |
|
highway project. |
|
(b) The engineer selected for a state highway project under |
|
Section 223.041 may not serve, alone or in combination with another |
|
person, as the construction manager for that project. |
|
(c) Subsection (b) does not prohibit the engineer from |
|
providing customary construction phase services under the |
|
engineer's contract with the department in accordance with |
|
applicable licensing laws. |
|
Sec. 223.305. ADOPTION OF CRITERIA AND RULES. (a) The |
|
department shall adopt weighted selection criteria and rules for |
|
the selection process and award of contracts under this subchapter, |
|
which may include interviews with top-ranked offerors. |
|
(b) The rules adopted under Subsection (a) must address the |
|
selection process applicable to the award of a contract for |
|
preconstruction services and for construction management and |
|
construction services, including the process for contract |
|
negotiations with the construction manager for construction of the |
|
project or work packages associated with the project in accordance |
|
with contract documents. |
|
Sec. 223.306. EVALUATION TEAM. (a) Before preparing a |
|
request under Section 223.307 for a state highway project, the |
|
director shall appoint a team of at least three members to assist |
|
the department in evaluating proposals and qualifications received |
|
by the department. The members may be department employees or |
|
outside consultants. |
|
(b) At least one-half, or as near one-half as possible, of |
|
the team members must be engineers registered in this state. An |
|
engineer who serves on the team and is not a department employee may |
|
not otherwise be involved in the project for which the request is |
|
prepared under Section 223.307. |
|
(c) The team must include at least one person who is a senior |
|
management employee of a general contractor that: |
|
(1) is registered as a prequalified general contractor |
|
under department rules; |
|
(2) is not involved in the project for which the |
|
request is prepared under Section 223.307; and |
|
(3) has no other conflict of interest as determined by |
|
the department. |
|
Sec. 223.307. SELECTION PROCESS. (a) The department may |
|
select the construction manager in a one-step or two-step process. |
|
(b) The department shall prepare a single request for |
|
proposals, in the case of a one-step process, and an initial request |
|
for qualifications followed by a request for proposals and any |
|
required interviews, in the case of a two-step process. A request |
|
prepared under this subsection must include: |
|
(1) a statement as to whether the selection process is |
|
a one-step or two-step process; |
|
(2) information regarding the project's location, |
|
scope, and limits; |
|
(3) publicly available cost estimates and a budget for |
|
the project; |
|
(4) information regarding funding that may be |
|
available for the project; |
|
(5) the selection criteria adopted under Section |
|
223.305 and the relative weighted value for each criterion; |
|
(6) the time and place for receipt of qualifications |
|
or proposals, as applicable; and |
|
(7) any other information that may assist the |
|
department in the selection of a construction manager. |
|
(c) If a one-step process is used, the department may |
|
request, as part of the offeror's proposal, the offeror's: |
|
(1) proposed billable rates for preconstruction |
|
services personnel; |
|
(2) proposed fee for home office overhead; and |
|
(3) profit fee on the negotiated construction price |
|
for performing construction services. |
|
(d) If a two-step process is used, the department may not |
|
request proposed billable rates, fees, or prices in step one. In |
|
step two, the department may request that five or fewer offerors, |
|
selected on the basis of qualifications, experience, technical |
|
competence, and ability to develop the project, provide additional |
|
information, including the offeror's: |
|
(1) proposed billable rates for preconstruction |
|
services and general conditions personnel; |
|
(2) proposed fee for home office overhead; and |
|
(3) profit fee on the negotiated construction price |
|
for performing construction services. |
|
(e) If a one-step process is used, proposed billable rates |
|
for general conditions personnel must be negotiated on selection of |
|
the construction manager. |
|
Sec. 223.308. SELECTION OF CONSTRUCTION MANAGER. (a) The |
|
department shall: |
|
(1) rank the offerors in accordance with the selection |
|
criteria provided in the request for proposals under Section |
|
223.307(b)(5); and |
|
(2) select the offeror that submits the proposal with |
|
the highest ranking. |
|
(b) The award of a preconstruction services contract under |
|
Subsection (a) authorizes the construction manager to: |
|
(1) provide consultation to the department and project |
|
engineer; and |
|
(2) enter into open and transparent negotiations with |
|
the department during the design phase of the project to refine the |
|
project's cost and schedule for the construction management and |
|
construction services contract. |
|
(c) The department shall use the services of an independent |
|
cost estimator for each work package associated with the project to |
|
validate the negotiated costs for the construction management and |
|
construction services contract. The independent cost estimator |
|
shall follow procedures outlined in the Federal Highway |
|
Administration Major Project Program Cost Estimating Guidance, as |
|
it existed on September 1, 2023, and as adapted by the department. |
|
(d) On successful negotiations under Subsection (b)(2), the |
|
department shall execute a construction management and |
|
construction services contract with the construction manager for |
|
either construction of the project or selected work packages |
|
associated with the project. |
|
(e) Negotiations under Subsection (b)(2) shall be |
|
terminated if the department is unable to reach a price agreement |
|
with the construction manager. If negotiations are terminated, the |
|
department may competitively bid the construction of the project in |
|
accordance with the department's procedures under Subchapter A. |
|
(f) Not later than the seventh day after the date a |
|
preconstruction services contract is awarded under this section, |
|
the department shall make public the selection rankings determined |
|
under Subsection (a). |
|
Sec. 223.309. PERFORMANCE OF WORK. (a) A construction |
|
manager shall perform a minimum percentage of construction work, |
|
excluding general conditions work, as required by the department's |
|
rules regarding standard specifications for highway and bridge |
|
construction. |
|
(b) A construction manager shall publicly advertise for |
|
bids or proposals and receive bids or proposals from subcontractors |
|
for the performance of the remaining construction work. |
|
Sec. 223.310. PERFORMANCE OR PAYMENT BOND. The |
|
construction manager shall deliver any performance and payment |
|
bonds not later than the 10th day after the date the construction |
|
manager is awarded a preconstruction services contract under |
|
Section 223.308 unless the construction manager furnishes a bid |
|
bond or other financial security acceptable to the department to |
|
ensure that the construction manager will furnish the required |
|
performance and payment bonds when a guaranteed maximum price is |
|
established. |
|
SECTION 2. This Act takes effect immediately if it receives |
|
a vote of two-thirds of all the members elected to each house, as |
|
provided by Section 39, Article III, Texas Constitution. If this |
|
Act does not receive the vote necessary for immediate effect, this |
|
Act takes effect September 1, 2023. |