|
|
|
A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to facilities and construction machinery used to respond |
|
to power outages. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 39.918, Utilities Code, is amended to |
|
read as follows: |
|
Sec. 39.918. UTILITY FACILITIES FOR RESPONDING TO |
|
SIGNIFICANT [POWER RESTORATION AFTER WIDESPREAD] POWER |
|
OUTAGE. (a) In this section, "significant ["widespread] power |
|
outage" means an event that [results in]: |
|
(1) results in a loss of electric power that: |
|
(A) affects a significant number of distribution |
|
customers of a transmission and distribution utility, creates a |
|
risk to public health or safety,[;] and |
|
[(B)] has lasted or is expected to last for at |
|
least six [eight] hours; |
|
(B) affects distribution customers of a |
|
transmission and distribution utility in an area for which the |
|
governor has issued a disaster or emergency declaration; |
|
(C) affects customers served by a radial |
|
transmission or distribution facility, creates a risk to public |
|
health or safety, and has lasted or is expected to last for at least |
|
twelve hours; or |
|
(D) creates [and |
|
[(2)] a risk to public health or safety because it |
|
affects a critical infrastructure facility, hospital, health care |
|
facility, law enforcement facility, fire station, or water or |
|
wastewater facility; or |
|
(2) causes the independent system operator to order a |
|
transmission and distribution utility to shed load. |
|
(a-1) The Texas Division of Emergency Management, the |
|
independent organization certified under Section 39.151 for the |
|
ERCOT power region, or the executive director of the commission may |
|
determine that a power outage other than an outage described by |
|
Subsection (a) is a significant power outage for the purposes of |
|
this section. |
|
(b) Notwithstanding any other provision of this subtitle, a |
|
transmission and distribution utility may: |
|
(1) lease or own and operate facilities that provide |
|
temporary emergency electric energy to aid in providing power to |
|
the utility's distribution customers when a significant power |
|
outage is imminent or restoring power to the utility's distribution |
|
customers during a significant [widespread] power outage [in which: |
|
[(A) the independent system operator has ordered |
|
the utility to shed load; or |
|
[(B) the utility's distribution facilities are |
|
not being fully served by the bulk power system under normal |
|
operations]; and |
|
(2) procure, own, and operate, or enter into a |
|
cooperative agreement with other transmission and distribution |
|
utilities to procure, own, and operate jointly, transmission and |
|
distribution facilities that have a lead time of at least six months |
|
and would aid in restoring power to the utility's distribution |
|
customers following a significant [widespread] power outage. |
|
(b-1) In this section, long lead time facilities described |
|
by Subsection (b) may not be electric energy storage equipment or |
|
facilities described by [under] Chapter 35[, Utilities Code]. |
|
(c) A transmission and distribution utility that [leases |
|
and] operates a facility [facilities] under Subsection (b)(1) may |
|
not sell electric energy or ancillary services from the facility |
|
[those facilities]. |
|
(d) A facility [Facilities] described by Subsection (b)(1): |
|
(1) must be operated in isolation from the bulk power |
|
system; and |
|
(2) may not be included in independent system |
|
operator: |
|
(A) locational marginal pricing calculations; |
|
(B) pricing; or |
|
(C) reliability models. |
|
(e) A transmission and distribution utility that [leases |
|
and] operates a facility [facilities] under Subsection (b)(1) shall |
|
ensure, to the extent reasonably practicable, that retail customer |
|
usage during operation of the facility [those facilities] is |
|
adjusted out of the usage reported for billing purposes by the |
|
retail customer's retail electric provider. |
|
(f) A transmission and distribution utility shall, when |
|
reasonably practicable, use a competitive bidding process to lease |
|
a facility [facilities] under Subsection (b)(1). |
|
(g) A transmission and distribution utility that leases or |
|
owns and operates facilities under Subsection (b)(1) or that |
|
procures, owns, and operates facilities under Subsection (b)(2) |
|
shall include in the utility's emergency operations plan filed with |
|
the commission, as described by Section 186.007, a detailed plan on |
|
the utility's use of those facilities. |
|
(h) The commission shall allow [permit]: |
|
(1) a transmission and distribution utility that |
|
leases or owns and operates facilities under Subsection (b)(1) to |
|
recover the reasonable and necessary costs of leasing or owning and |
|
operating the facilities, including the present value of future |
|
payments required under a [the] lease, using the rate of return on |
|
investment established in the commission's final order in the |
|
utility's most recent base rate proceeding; and |
|
(2) a transmission and distribution utility that |
|
procures, owns, and operates facilities under Subsection (b)(2) to |
|
recover the reasonable and necessary costs of procuring, owning, |
|
and operating the facilities, using the rate of return on |
|
investment established in the commission's final order in the |
|
utility's most recent base rate proceeding. |
|
(i) The commission shall authorize a transmission and |
|
distribution utility to defer for recovery in a future ratemaking |
|
proceeding the incremental operations and maintenance expenses and |
|
the return, not otherwise recovered in a rate proceeding, |
|
associated with the leasing, [or] procurement, ownership, and |
|
operation of the facilities. |
|
(j) A transmission and distribution utility may request |
|
recovery of the reasonable and necessary costs of leasing, [or] |
|
procuring, owning, or [and] operating facilities under this |
|
section, including any deferred expenses, through an expedited |
|
periodic rate adjustment [a] proceeding under Section 36.210 or in |
|
another ratemaking proceeding. The commission may review costs |
|
recovered through a periodic rate adjustment in the following base |
|
rate proceeding and order refunds to customers if appropriate. |
|
(k) A transmission and distribution utility requesting cost |
|
recovery under Subsection (j) is entitled to select whether the |
|
costs are considered to be distribution substation equipment costs |
|
or distribution transformer costs unless the commission has found |
|
in a previous base rate proceeding for the utility that temporary |
|
emergency electric energy costs should be categorized in a |
|
different manner. A lease under Subsection (b)(1) must be treated |
|
as a capital lease or finance lease for ratemaking purposes. |
|
(l) The fact that the commission has not previously approved |
|
a facility operated under this section or a cost of leasing, |
|
procuring, owning, or operating a facility under this section is |
|
not grounds for dismissal of the facility or the cost from a |
|
proceeding under Section 36.210 or another ratemaking proceeding. |
|
(m) If the capacity of facilities a transmission and |
|
distribution utility operates under Subsection (b)(1) is less than |
|
or equal to three percent of the utility's historical peak load, the |
|
commission shall find that: |
|
(1) the facilities are used and useful to the utility |
|
in providing service; and |
|
(2) the costs of leasing or owning and operating the |
|
facilities are prudent, reasonable, and necessary. |
|
[(k) This section expires September 1, 2029.] |
|
SECTION 2. Section 502.146(b), Transportation Code, is |
|
amended to read as follows: |
|
(b) An owner is not required to register a vehicle that is |
|
used only temporarily on the highways if the vehicle is: |
|
(1) a farm trailer or farm semitrailer with a gross |
|
weight of more than 4,000 pounds but not more than 34,000 pounds |
|
that is used exclusively: |
|
(A) to transport seasonally harvested |
|
agricultural products or livestock from the place of production to |
|
the place of processing, market, or storage; |
|
(B) to transport farm supplies from the place of |
|
loading to the farm; or |
|
(C) for the purpose of participating in equine |
|
activities or attending livestock shows, as defined by Section |
|
87.001, Civil Practice and Remedies Code; |
|
(2) machinery used exclusively for the purpose of |
|
drilling water wells; |
|
(3) oil well servicing or drilling machinery and if at |
|
the time of obtaining the license plates, the applicant submits |
|
proof that the applicant has a permit under Section 623.142; or |
|
(4) construction machinery, including construction |
|
machinery that is: |
|
(A) owned by a transmission and distribution |
|
utility as defined by Section 31.002, Utilities Code; and |
|
(B) used to maintain or repair electrical lines |
|
or substations in response to a power outage. |
|
SECTION 3. The changes in law made by this Act apply only to |
|
a proceeding before the Public Utility Commission of Texas, or |
|
other regulatory authority described by Section 11.003, Utilities |
|
Code, that commences on or after the effective date of this Act. A |
|
proceeding before the Public Utility Commission of Texas or other |
|
regulatory authority described by Section 11.003, Utilities Code, |
|
that commenced before the effective date of this Act is governed by |
|
the law in effect on the date the proceeding commenced, and that law |
|
is continued in effect for that purpose. |
|
SECTION 4. To the extent of any conflict, this Act prevails |
|
over another Act of the 88th Legislature, Regular Session, 2023, |
|
relating to nonsubstantive additions to and corrections in enacted |
|
codes. |
|
SECTION 5. This Act takes effect September 1, 2023. |