  By: Geren (Senate Sponsor - Schwertner) H.B. No. 5066
         (In the Senate - Received from the House May 8, 2023;
  May 9, 2023, read first time and referred to Committee on Business &
  Commerce; May 18, 2023, reported adversely, with favorable
  Committee Substitute by the following vote:  Yeas 9, Nays 0;
  May 18, 2023, sent to printer.)
Click here to see the committee vote
 
  COMMITTEE SUBSTITUTE FOR H.B. No. 5066 By:  Nichols
 
 
A BILL TO BE ENTITLED
 
AN ACT
 
  relating to electricity service in areas of this state with a need
  for transmission projects.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Sections 37.056(c) and (c-1), Utilities Code,
  are amended to read as follows:
         (c)  The commission shall grant each certificate on a
  nondiscriminatory basis after considering:
               (1)  the adequacy of existing service;
               (2)  the need for additional service;
               (3)  the effect of granting the certificate on the
  recipient of the certificate and any electric utility serving the
  proximate area; and
               (4)  other factors, such as:
                     (A)  community values;
                     (B)  recreational and park areas;
                     (C)  historical and aesthetic values;
                     (D)  environmental integrity;
                     (E)  the probable improvement of service or
  lowering of cost to consumers in the area if the certificate is
  granted, including any potential economic or reliability benefits
  associated with dual fuel and fuel storage capabilities in areas
  outside the ERCOT power region; and
                     (F)  the need for extending transmission service
  where existing or projected electrical loads will be underserved,
  including where:
                           (i)  the existing transmission service is
  unreasonably remote;
                           (ii)  the available capacity is unreasonably
  limited at transmission or distribution voltage level; or
                           (iii)  the electrical load cannot be
  interconnected in a timely manner [to the extent applicable, the
  effect of granting the certificate on the ability of this state to
  meet the goal established by Section 39.904(a) of this title].
         (c-1)  In considering the need for additional service under
  Subsection (c)(2) for a reliability transmission project that
  serves the ERCOT power region or under Subsection (c)(4)(F), the
  commission must consider the historical load, forecasted load
  growth, and additional load currently seeking interconnection,
  including load for which the electric utility has yet to sign an
  interconnection agreement, as determined by the electric utility
  with the responsibility for serving the load.
         SECTION 2.  Section 37.057, Utilities Code, is amended to
  read as follows:
         Sec. 37.057.  DEADLINE FOR APPLICATION FOR NEW TRANSMISSION
  FACILITY. The commission must approve or deny an application for a
  certificate for a new transmission facility not later than the
  180th day after [the first anniversary of] the date the application
  is filed. If the commission does not approve or deny the
  application on or before that date, a party may seek a writ of
  mandamus in a district court of Travis County to compel the
  commission to decide on the application.
         SECTION 3.  Subchapter D, Chapter 39, Utilities Code, is
  amended by adding Sections 39.166 and 39.167 to read as follows:
         Sec. 39.166.  RELIABILITY PLAN FOR REGIONS WITH RAPID
  ELECTRICAL LOAD GROWTH. (a)  The commission shall direct the
  independent organization certified under Section 39.151 for the
  ERCOT power region to:
               (1)  identify each region in which transmission
  capacity is insufficient to meet the region's existing and
  forecasted electrical load, as reasonably determined by the
  certificated transmission service provider; and
               (2)  develop a reliability plan to serve existing and
  forecasted electrical load in the identified region.
         (b)  The commission shall develop a plan to implement each
  reliability plan adopted under Subsection (a) to ensure timely
  development and approval of necessary transmission service
  improvements.
         Sec. 39.167.  RELIABILITY PLAN FOR PERMIAN BASIN. (a) Not
  later than January 30, 2024, the commission shall direct the
  independent organization certified under Section 39.151 for the
  ERCOT power region to develop a reliability plan under Section
  39.166 for the Permian Basin region.
         (b)  The plan must:
               (1)  address extending transmission service to areas
  where mineral resources have been found;
               (2)  address increasing available capacity to meet
  forecasted load; and
               (3)  provide available infrastructure to reduce
  interconnection times in areas without access to transmission
  service.
         (c)  This section expires September 1, 2025.
         SECTION 4.  The changes in law made by this Act apply only to
  a proceeding affecting a certificate of public convenience and
  necessity that commences on or after the effective date of this Act.
  A proceeding affecting a certificate of public convenience and
  necessity that commenced before the effective date of this Act is
  governed by the law in effect on the date the proceeding is
  commenced, and that law is continued in effect for that purpose.
         SECTION 5.  This Act takes effect immediately if it receives
  a vote of two-thirds of all the members elected to each house, as
  provided by Section 39, Article III, Texas Constitution.  If this
  Act does not receive the vote necessary for immediate effect, this
  Act takes effect September 1, 2023.
 
  * * * * *