A BILL TO BE ENTITLED
|
|
|
AN ACT
|
|
|
relating to the regulation of bulk-power system equipment by the |
|
|
Public Utility Commission of Texas. |
|
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
|
SECTION 1. Chapter 32, Utilities Code, is amended by adding |
|
|
Subchapter D to read as follows: |
|
|
SUBCHAPTER D. BULK-POWER SYSTEM TRANSACTIONS |
|
|
Sec. 32.151. DEFINITIONS. In this subchapter: |
|
|
(1) "Bulk-power system" means: |
|
|
(A) the facilities and control systems necessary |
|
|
for operating an interconnected electric energy transmission |
|
|
network or a portion of a network, other than: |
|
|
(i) transmission lines rated at less than |
|
|
69,000 volts; and |
|
|
(ii) facilities used in the local |
|
|
distribution of electric energy; and |
|
|
(B) electric energy from generation facilities |
|
|
needed to maintain transmission reliability. |
|
|
(2) "Bulk-power system equipment" means items used in |
|
|
bulk-power system substations, control rooms, or power generating |
|
|
stations, including reactors, capacitors, substation transformers, |
|
|
current coupling capacitors, large generators, backup generators, |
|
|
substation voltage regulators, shunt capacitor equipment, |
|
|
automatic circuit reclosers, instrument transformers, coupling |
|
|
capacity voltage transformers, protective relaying, metering |
|
|
equipment, high voltage circuit breakers, generation turbines, |
|
|
industrial control systems, distributed control systems, and |
|
|
safety instrumented systems. |
|
|
Sec. 32.152. BULK-POWER SYSTEM TRANSACTIONS. (a) The |
|
|
commission by rule shall prohibit the acquisition, importation, |
|
|
transfer, or installation of bulk-power system equipment in this |
|
|
state that: |
|
|
(1) was designed, developed, manufactured, or |
|
|
supplied by persons owned by, controlled by, or subject to the |
|
|
jurisdiction of China, Iran, Russia, or a country designated by the |
|
|
governor as a threat to critical infrastructure under Section |
|
|
113.003, Business & Commerce Code, as added by Chapter 975 (S.B. |
|
|
2116), Acts of the 87th Legislature, Regular Session, 2021; or |
|
|
(2) is part of a transaction that the commission |
|
|
determines presents an undue security or safety risk to the |
|
|
bulk-power system in this state because of potential: |
|
|
(A) sabotage to or subversion of the design, |
|
|
integrity, manufacturing, production, distribution, installation, |
|
|
operation, or maintenance of the bulk-power system in this state; |
|
|
or |
|
|
(B) catastrophic effects for the security or |
|
|
resiliency of critical infrastructure or the economy of this state. |
|
|
(b) The commission shall: |
|
|
(1) design or negotiate measures to mitigate risks |
|
|
described by Subsection (a); and |
|
|
(2) require that a person acquiring, importing, |
|
|
transferring, or installing bulk-power system equipment in this |
|
|
state incorporate a mitigation measure in the acquisition, |
|
|
importation, transfer, or installation if the commission |
|
|
determines that the measure is necessary to mitigate risks |
|
|
described by Subsection (a). |
|
|
(c) The commission shall: |
|
|
(1) establish and publish criteria for pre-approving |
|
|
particular equipment and particular vendors in the bulk-power |
|
|
system equipment market as compliant with this section; and |
|
|
(2) publish a list of pre-approved equipment and |
|
|
vendors. |
|
|
SECTION 2. Subchapter D, Chapter 32, Utilities Code, as |
|
|
added by this Act, applies only to a contract for the acquisition, |
|
|
importation, transfer, or installation of bulk-power system |
|
|
equipment entered into on or after the effective date of this Act. |
|
|
SECTION 3. It is the intent of the 88th Legislature, Regular |
|
|
Session, 2023, that the amendments made by this Act be harmonized |
|
|
with another Act of the 88th Legislature, Regular Session, 2023, |
|
|
relating to nonsubstantive additions to and corrections in enacted |
|
|
codes. |
|
|
SECTION 4. This Act takes effect September 1, 2023. |