| |
|
|
A BILL TO BE ENTITLED
|
|
|
AN ACT
|
| |
|
|
relating to facilities and construction machinery used to respond |
|
|
to power outages. |
|
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
|
SECTION 1. Section 39.918, Utilities Code, is amended to |
|
|
read as follows: |
|
|
Sec. 39.918. UTILITY FACILITIES FOR RESPONDING TO |
|
|
SIGNIFICANT [POWER RESTORATION AFTER WIDESPREAD] POWER |
|
|
OUTAGE. (a) In this section, "significant ["widespread] power |
|
|
outage" means an event that [results in]: |
|
|
(1) results in a loss of electric power that: |
|
|
(A) affects a significant number of distribution |
|
|
customers of a transmission and distribution utility[;] and |
|
|
[(B)] has lasted or is expected to last for at |
|
|
least six [eight] hours; |
|
|
(B) affects distribution customers of a |
|
|
transmission and distribution utility in an area for which the |
|
|
governor has issued a disaster or emergency declaration; |
|
|
(C) affects distribution customers served by a |
|
|
radial transmission or distribution facility, creates a risk to |
|
|
public health or safety, and has lasted or is expected to last for |
|
|
at least 12 hours; or |
|
|
(D) creates [and |
|
|
[(2)] a risk to public health or safety because it |
|
|
affects a critical infrastructure facility that serves the public |
|
|
such as a hospital, health care facility, law enforcement facility, |
|
|
fire station, or water or wastewater facility; or |
|
|
(2) causes the independent system operator to order a |
|
|
transmission and distribution utility to shed load. |
|
|
(a-1) The Texas Division of Emergency Management, the |
|
|
independent organization certified under Section 39.151 for the |
|
|
ERCOT power region, or the executive director of the commission may |
|
|
determine that a power outage other than an outage described by |
|
|
Subsection (a) is a significant power outage for the purposes of |
|
|
this section. |
|
|
(a-2) A transmission and distribution utility is entitled |
|
|
to determine whether a loss of electric power described by |
|
|
Subsection (a)(1)(C) creates a risk to public health or safety for |
|
|
the purposes of determining whether the loss event is a significant |
|
|
power outage. |
|
|
(b) Notwithstanding any other provision of this subtitle, a |
|
|
transmission and distribution utility may: |
|
|
(1) lease or own and operate facilities that provide |
|
|
temporary emergency electric energy to aid in restoring power to |
|
|
the utility's distribution customers during a significant |
|
|
[widespread] power outage [in which: |
|
|
[(A) the independent system operator has ordered |
|
|
the utility to shed load; or |
|
|
[(B) the utility's distribution facilities are |
|
|
not being fully served by the bulk power system under normal |
|
|
operations]; and |
|
|
(2) procure, own, and operate, or enter into a |
|
|
cooperative agreement with other transmission and distribution |
|
|
utilities to procure, own, and operate jointly, transmission and |
|
|
distribution facilities that have a lead time of at least six months |
|
|
and would aid in restoring power to the utility's distribution |
|
|
customers following a significant [widespread] power outage. |
|
|
(b-1) In this section, long lead time facilities described |
|
|
by Subsection (b) may not be electric energy storage equipment or |
|
|
facilities described by [under] Chapter 35[, Utilities Code]. |
|
|
(c) A transmission and distribution utility that [leases |
|
|
and] operates a facility [facilities] under Subsection (b)(1) may |
|
|
not sell electric energy or ancillary services from the facility |
|
|
[those facilities]. As soon as reasonably practicable after the |
|
|
utility deploys the facility, the utility shall provide written |
|
|
notice to the commission and a written market notice to advise |
|
|
competitive market participants of the details of the deployment. |
|
|
Not later than the fifth business day after the date the deployment |
|
|
ends, the utility shall file a report, in a form approved by the |
|
|
commission, providing the details of the deployment, including the |
|
|
start and end times of the deployment, the number of kilowatts or |
|
|
megawatts deployed, the number of facilities used, the locations of |
|
|
the facilities, and any other information required by the |
|
|
commission. |
|
|
(d) A facility [Facilities] described by Subsection (b)(1): |
|
|
(1) must be operated in isolation from the bulk power |
|
|
system; and |
|
|
(2) may not be included in independent system |
|
|
operator: |
|
|
(A) locational marginal pricing calculations; |
|
|
(B) pricing; or |
|
|
(C) reliability models. |
|
|
(e) A transmission and distribution utility that [leases |
|
|
and] operates a facility [facilities] under Subsection (b)(1) shall |
|
|
ensure, to the extent reasonably practicable, that retail customer |
|
|
usage during operation of the facility [those facilities] is |
|
|
adjusted out of the usage reported for billing purposes by the |
|
|
retail customer's retail electric provider. |
|
|
(f) A transmission and distribution utility that decides to |
|
|
lease a facility under Subsection (b)(1) shall, when reasonably |
|
|
practicable, solicit [use a] competitive bids and consider any bids |
|
|
received before leasing the facility [bidding process to lease |
|
|
facilities under Subsection (b)(1)]. |
|
|
(g) A transmission and distribution utility that leases or |
|
|
owns and operates facilities under Subsection (b)(1) or that |
|
|
procures, owns, and operates facilities under Subsection (b)(2) |
|
|
shall include in the utility's emergency operations plan filed with |
|
|
the commission, as described by Section 186.007, a detailed plan on |
|
|
the utility's use of those facilities. |
|
|
(h) The commission shall allow [permit]: |
|
|
(1) a transmission and distribution utility that |
|
|
leases or owns and operates facilities under Subsection (b)(1) to |
|
|
recover the reasonable and necessary costs of leasing or owning and |
|
|
operating the facilities, including the present value of future |
|
|
payments required under a [the] lease, using the rate of return on |
|
|
investment established in the commission's final order in the |
|
|
utility's most recent base rate proceeding; and |
|
|
(2) a transmission and distribution utility that |
|
|
procures, owns, and operates facilities under Subsection (b)(2) to |
|
|
recover the reasonable and necessary costs of procuring, owning, |
|
|
and operating the facilities, using the rate of return on |
|
|
investment established in the commission's final order in the |
|
|
utility's most recent base rate proceeding. |
|
|
(i) The commission shall authorize a transmission and |
|
|
distribution utility to defer for recovery in a future ratemaking |
|
|
proceeding the incremental operations and maintenance expenses and |
|
|
the return, not otherwise recovered in a rate proceeding, |
|
|
associated with the leasing, [or] procurement, ownership, and |
|
|
operation of the facilities. |
|
|
(j) A transmission and distribution utility may request |
|
|
recovery of the reasonable and necessary costs of leasing, [or] |
|
|
procuring, owning, or [and] operating facilities under this |
|
|
section, including any deferred expenses, through a proceeding |
|
|
under Section 36.210 or in another ratemaking proceeding. The |
|
|
commission may review costs recovered through a proceeding under |
|
|
Section 36.210 in the following base rate proceeding and order |
|
|
refunds to customers if appropriate. |
|
|
(k) A transmission and distribution utility requesting cost |
|
|
recovery under Subsection (j) is entitled to select whether the |
|
|
costs are considered to be distribution substation equipment costs |
|
|
or distribution transformer costs unless the commission has found |
|
|
in a previous base rate proceeding for the utility that temporary |
|
|
emergency electric energy costs should be categorized in a |
|
|
different manner. The costs may not be considered transmission |
|
|
costs. A lease under Subsection (b)(1) must be treated as a capital |
|
|
lease or finance lease for ratemaking purposes. |
|
|
(l) The fact that the commission has not previously approved |
|
|
a facility operated under this section or a cost of leasing, |
|
|
procuring, owning, or operating a facility under this section is |
|
|
not grounds for dismissal of the facility or the cost from a |
|
|
proceeding under Section 36.210 or another ratemaking proceeding. |
|
|
(m) The total capacity of facilities a transmission and |
|
|
distribution utility leases or owns and operates under Subsection |
|
|
(b)(1) may not exceed three percent of the utility's historical |
|
|
peak load. Each transmission and distribution utility that leases |
|
|
or owns and operates a facility under Subsection (b)(1) shall: |
|
|
(1) assess every four years the total capacity of |
|
|
facilities needed to aid in restoring power during a significant |
|
|
power outage, considering: |
|
|
(A) the presence and frequency of extreme weather |
|
|
conditions, including hurricanes, tornadoes, high winds, |
|
|
lightning, flooding, icing, and freezes, in all or a portion of the |
|
|
utility's certificated service area; |
|
|
(B) the utility's current and planned system |
|
|
hardening efforts; |
|
|
(C) the utility's current and planned vegetation |
|
|
management efforts; |
|
|
(D) the utility's current and planned |
|
|
expenditures on traditional distribution facilities; |
|
|
(E) the utility's current and planned |
|
|
expenditures on automation of its distribution system; |
|
|
(F) the utility's allocated load shed obligation |
|
|
based on historical seasonal peak demand, as determined by the |
|
|
independent system operator; |
|
|
(G) the presence or number of communities that |
|
|
are remotely located or served radially in the utility's |
|
|
certificated service area; |
|
|
(H) the number or location of critical |
|
|
infrastructure facilities that serve the public such as hospitals, |
|
|
health care facilities, law enforcement facilities, fire stations, |
|
|
and water or wastewater facilities in the utility's certificated |
|
|
service area; |
|
|
(I) the utility's emergency operations plan |
|
|
filed with the commission; and |
|
|
(J) other engineering or operational needs; and |
|
|
(2) submit to the commission the assessment under |
|
|
Subdivision (1) for review. |
|
|
(n) The commission: |
|
|
(1) may: |
|
|
(A) notwithstanding the total capacity |
|
|
prescribed by Subsection (m), establish the capacity of facilities |
|
|
that may be operated by a transmission and distribution utility in |
|
|
aid of restoration for each type or category of significant power |
|
|
outage, with the total capacity equal to or greater than three |
|
|
percent of the utility's historical peak load; |
|
|
(B) establish reasonable conditions on the |
|
|
operation and use of facilities, including duration times and |
|
|
prioritizing use to serve critical infrastructure facilities that |
|
|
serve the public such as hospitals, health care facilities, law |
|
|
enforcement facilities, fire stations, and water or wastewater |
|
|
facilities; and |
|
|
(C) require compliance with applicable law, |
|
|
including any rule or order of the commission; and |
|
|
(2) shall establish a rebuttable presumption that the |
|
|
facilities leased or owned and operated under Subsection (m) are |
|
|
used and useful to the utility in providing service and the |
|
|
utility's costs of leasing or owning and operating the facilities |
|
|
are prudent, reasonable, necessary, and recoverable under Section |
|
|
36.210 or in another ratemaking proceeding. |
|
|
(o) Notwithstanding Subsections (m) and (n), a transmission |
|
|
and distribution utility may: |
|
|
(1) provide facilities to or use facilities from other |
|
|
entities as part of a mutual assistance agreement during a |
|
|
significant power outage; and |
|
|
(2) lease facilities on a short-term basis in response |
|
|
to a significant power outage if: |
|
|
(A) the significant power outage constitutes an |
|
|
emergency and the utility determines that additional facilities are |
|
|
necessary; |
|
|
(B) the term of the lease is only for the duration |
|
|
of that emergency; |
|
|
(C) the utility notifies the commission of the |
|
|
lease not later than the 30th day after the date of the lease |
|
|
agreement; and |
|
|
(D) the commission reviews the costs incurred by |
|
|
the utility in a proceeding under Section 36.210 or in another |
|
|
ratemaking proceeding. |
|
|
[(k) This section expires September 1, 2029.] |
|
|
SECTION 2. Section 502.146(b), Transportation Code, is |
|
|
amended to read as follows: |
|
|
(b) An owner is not required to register a vehicle that is |
|
|
used only temporarily on the highways if the vehicle is: |
|
|
(1) a farm trailer or farm semitrailer with a gross |
|
|
weight of more than 4,000 pounds but not more than 34,000 pounds |
|
|
that is used exclusively: |
|
|
(A) to transport seasonally harvested |
|
|
agricultural products or livestock from the place of production to |
|
|
the place of processing, market, or storage; |
|
|
(B) to transport farm supplies from the place of |
|
|
loading to the farm; or |
|
|
(C) for the purpose of participating in equine |
|
|
activities or attending livestock shows, as defined by Section |
|
|
87.001, Civil Practice and Remedies Code; |
|
|
(2) machinery used exclusively for the purpose of |
|
|
drilling water wells; |
|
|
(3) oil well servicing or drilling machinery and if at |
|
|
the time of obtaining the license plates, the applicant submits |
|
|
proof that the applicant has a permit under Section 623.142; or |
|
|
(4) construction machinery, including construction |
|
|
machinery that is: |
|
|
(A) owned by a transmission and distribution |
|
|
utility as defined by Section 31.002, Utilities Code; and |
|
|
(B) used to maintain or repair electrical lines |
|
|
or substations in response to a power outage. |
|
|
SECTION 3. (a) The changes in law made in Section 1 of this |
|
|
Act apply only to a proceeding before the Public Utility Commission |
|
|
of Texas or other regulatory authority described by Section 11.003, |
|
|
Utilities Code, that commences on or after the effective date of |
|
|
this Act. A proceeding before the Public Utility Commission of |
|
|
Texas or other regulatory authority described by Section 11.003, |
|
|
Utilities Code, that commenced before the effective date of this |
|
|
Act is governed by the law in effect on the date the proceeding |
|
|
commenced, and that law is continued in effect for that purpose. |
|
|
(b) The changes in law made in Section 1 of this Act apply |
|
|
only to a contract or lease entered into or facilities procured on |
|
|
or after the effective date of this Act. |
|
|
SECTION 4. To the extent of any conflict, this Act prevails |
|
|
over another Act of the 88th Legislature, Regular Session, 2023, |
|
|
relating to nonsubstantive additions to and corrections in enacted |
|
|
codes. |
|
|
SECTION 5. This Act takes effect September 1, 2023. |
|
|
|
|
|
* * * * * |