A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to a limitation on the generation capacity provided for |
|
the ERCOT power grid from wind and solar generation facilities. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 39.159, Utilities Code, as added by |
|
Chapter 426 (S.B. 3), Acts of the 87th Legislature, Regular |
|
Session, 2021, is amended by amending Subsection (b) and adding |
|
Subsection (d) to read as follows: |
|
(b) The commission shall ensure that the independent |
|
organization certified under Section 39.151 for the ERCOT power |
|
region: |
|
(1) subject to Subsection (d), establishes |
|
requirements to meet the reliability needs of the power region; |
|
(2) periodically, but at least annually, determines |
|
the quantity and characteristics of ancillary or reliability |
|
services necessary to ensure appropriate reliability during |
|
extreme heat and extreme cold weather conditions and during times |
|
of low non-dispatchable power production in the power region; |
|
(3) procures ancillary or reliability services on a |
|
competitive basis to ensure appropriate reliability during extreme |
|
heat and extreme cold weather conditions and during times of low |
|
non-dispatchable power production in the power region; |
|
(4) develops appropriate qualification and |
|
performance requirements for providing services under Subdivision |
|
(3), including appropriate penalties for failure to provide the |
|
services; and |
|
(5) sizes the services procured under Subdivision (3) |
|
to prevent prolonged rotating outages due to net load variability |
|
in high demand and low supply scenarios. |
|
(d) Beginning January 1, 2027, notwithstanding any other |
|
law, if the commission determines that installed generation |
|
capacity from wind and solar generation facilities is contributing |
|
more than 20 percent of the available generation capacity for the |
|
ERCOT power region, the commission shall: |
|
(1) prohibit the interconnection of new wind and solar |
|
generation facilities to the power grid; and |
|
(2) by rule establish standards for the disconnection |
|
of wind and solar power facilities from the power grid to ensure |
|
that wind and solar generation is not contributing more than 20 |
|
percent of the available generation capacity for the ERCOT power |
|
region at any time. |
|
SECTION 2. This Act takes effect September 1, 2023. |