Amend CSHB 14 (senate committee report) in SECTION 1 of the bill as follows:
(1)  In added Section 483.001(2), Government Code (page 1, lines 37 and 38), strike "office to be either of generation III" and substitute "regulatory commission to be either of generation III+".
(2)  Immediately after added Section 483.101(d), Government Code (page 2, between lines 41 and 42), insert the following appropriately designated subsection and reletter subsequent subsections accordingly:
( )  The office may not require an advanced nuclear project to be located in a specific location.
(3)  In added Section 483.101(f), Government Code (page 2, line 48), between "office" and "shall", insert "and the utility commission".
(4)  In added Section 483.102(d), Government Code (page 2, line 60, through page 3, line 1), strike Subdivisions (2) and (5) and renumber subsequent subdivisions accordingly.
(5)  In added Section 483.103, Government Code (page 3, lines 5 and 6), strike "governor and Legislative Budget Board" and substitute "the governor, the legislature, and the Legislative Budget Board".
(6)  Strike added Section 483.104(b), Government Code (page 3, lines 12 through 16), and substitute the following:
(b)  A nuclear permitting coordinator must have a demonstrated familiarity with the permitting and regulatory process in this state.
(7)  In added Section 483.104(c), Government Code (page 3, line 23), strike "assistance" and substitute "guidance".
(8)  In added Section 483.201(b)(1), Government Code (page 3, lines 45 and 46), between "to" and "businesses", insert "eligible".
(9)  In added Section 483.202(b), Government Code (page 3, line 56), strike "or the recipient's project partner's".
(10)  In added Section 483.202(d), Government Code (page 4, line 13), between "received" and "if", insert "from that grant".
(11)  In the heading to added Section 483.205, Government Code (page 5, line 24), strike "GRID-CAPABLE" and substitute "INTERCONNECTED".
(12)  In added Section 483.205(a), Government Code (page 5, lines 25 through 27), strike "and operation of an advanced nuclear reactor in this state that is capable of interconnection with the ERCOT power grid" and substitute "of an operational advanced nuclear reactor in this state that is interconnected with the ERCOT power grid".