A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to light pollution mitigation for wind turbine generators. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Subchapter A, Chapter 35, Utilities Code, is |
|
amended by adding Section 35.0023 to read as follows: |
|
Sec. 35.0023. WIND TURBINE LIGHT POLLUTION MITIGATION. (a) |
|
This section applies only to an electric utility, power generation |
|
company, or exempt wholesale generator that: |
|
(1) is required by the Federal Aviation Administration |
|
to use aviation obstruction lighting; and |
|
(2) sells at wholesale electric energy produced by a |
|
wind turbine generator. |
|
(b) The commission by rule shall require an electric |
|
utility, power generation company, or exempt wholesale generator to |
|
apply to the Federal Aviation Administration, or another applicable |
|
federal entity, for authorization to install and operate technology |
|
to mitigate light pollution from the wind turbine generator using a |
|
light mitigation technology system. |
|
(c) The rules adopted under Subsection (b) must require an |
|
electric utility, power generation company, or exempt wholesale |
|
generator that: |
|
(1) installs a wind turbine generator on or after |
|
December 31, 2026, to: |
|
(A) submit an application for approval of light |
|
mitigation technology to the Federal Aviation Administration not |
|
later than 180 days before the commercial operations date for the |
|
wind turbine generator; |
|
(B) install light mitigation technology on all |
|
wind turbine generators not later than 18 months after receiving |
|
approval of the technology from the Federal Aviation |
|
Administration; and |
|
(C) if installation of the light mitigation |
|
technology is delayed due to forces outside of the control of the |
|
utility, company, or generator, make a quarterly report to the |
|
commission detailing the reasons for the delay; or |
|
(2) installs a wind turbine generator before December |
|
31, 2026, to: |
|
(A) on repowering or not later than the 180th day |
|
after the execution of a newly signed long-term power purchase |
|
agreement, submit an application for approval of light mitigation |
|
technology to the Federal Aviation Administration; |
|
(B) install light mitigation technology on all |
|
wind turbine generators not later than 18 months after receiving |
|
approval of the technology from the Federal Aviation |
|
Administration; and |
|
(C) if installation of the light mitigation |
|
technology is delayed due to forces outside of the control of the |
|
utility, company, or generator, make a quarterly report to the |
|
commission detailing the reasons for the delay. |
|
(d) Subsection (c) applies only to a wind turbine generator |
|
with a commercial operations date that occurs after December 31, |
|
2008. |
|
(e) Notwithstanding Section 15.023(b), the total amount of |
|
an administrative penalty assessed for a violation continuing or |
|
occurring on separate days under this section may not exceed $1 |
|
million. |
|
SECTION 2. This Act takes effect September 1, 2025. |