89R20942 JXC-D
 
  By: Landgraf H.B. No. 1710
 
  Substitute the following for H.B. No. 1710:
 
  By:  Turner C.S.H.B. No. 1710
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to the issuance of a certificate of convenience or
  necessity for a facility to import or export power into or out of
  the ERCOT power region.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 37.051, Utilities Code, is amended by
  amending Subsections (c-1), (c-2), and (c-3) and adding Subsection
  (c-4) to read as follows:
         (c-1)  Notwithstanding any other provision of this title
  except Section 11.009, and except as provided by Subsection (c-3)
  [(c-2)], a person, including an electric utility or municipally
  owned utility, may not interconnect a facility to the ERCOT
  transmission grid that enables additional power to be imported into
  or exported out of the ERCOT power grid unless:
               (1)  the interconnection is approved by the Federal
  Energy Regulatory Commission under Section 210, 211, or 212 of the
  Federal Power Act (16 U.S.C. Section 824i, 824j, or 824k), and not
  under Section 203, 205, or 206 of the Federal Power Act (16 U.S.C.
  Section 824b, 824d, or 824e); and
               (2)  the person obtains a certificate from the
  commission stating that public convenience and necessity requires
  or will require the interconnection.
         (c-2)  A person described by Subsection (c-1) [The person]
  must apply for the certificate not later than the 180th day before
  the date the person seeks any order from the Federal Energy
  Regulatory Commission related to the interconnection. The
  commission shall apply Section 37.056 in considering an application
  under this subsection. In addition, the commission must determine
  that the application is consistent with the public interest before
  granting the certificate. The commission may adopt rules necessary
  to implement this subsection. This subsection does not apply to a
  facility that is in service on December 31, 2014.
         (c-3) [(c-2)]  The commission, not later than the 185th day
  after the date the application is filed, shall approve an
  application [filed under Subsection (c-1)] for a facility that is
  to be constructed under an interconnection agreement appended to an
  offer of settlement approved in a final order of the Federal Energy
  Regulatory Commission that was issued in Docket No. TX11-01-001 on
  or before December 31, 2014, directing physical connection between
  the ERCOT and SERC regions under Sections 210, 211, and 212 of the
  Federal Power Act (16 U.S.C. Sections 824i, 824j, and 824k). In
  approving the application, the commission may prescribe reasonable
  conditions to protect the public interest that are consistent with
  the final order of the Federal Energy Regulatory Commission.
         (c-4) [(c-3)]  Nothing in Subsection (c-1), [or] (c-2), or
  (c-3) is intended to restrict the authority of the commission or the
  independent organization certified under Section 39.151 for the
  ERCOT power region to adopt rules or protocols of general
  applicability.
         SECTION 2.  This Act takes effect September 1, 2025.