89R23391 SCR-D
 
  By: Darby H.B. No. 3069
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to the approval of a certificate of convenience and
  necessity for certain transmission projects.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  It is the intent of the legislature that the
  economic transmission planning required by this Act provides cost
  savings for consumers.
         SECTION 2.  Section 37.056, Utilities Code, is amended by
  adding Subsections (d-1) and (d-2) to read as follows:
         (d-1)  In addition to the criteria described by Subsections
  (c) and (d), the commission by rule shall establish supplemental
  multi-decade transmission planning criteria for granting a
  certificate for a transmission project that serves the ERCOT power
  region and that is not necessary to meet state or federal
  reliability standards.  The criteria must provide for an evaluation
  of potential savings for customers using methods such as discount
  rates, hurdle rates, averaging costs over a reasonable number of
  years, or scenario planning or any other method the commission
  considers appropriate.  The commission shall include with the
  commission's decision on an application for a certificate to which
  this subsection applies the commission's findings on the
  multi-decade transmission planning criteria.
         (d-2)  The commission may use an evaluation of a proposed
  transmission project conducted by the independent organization
  certified under Section 39.151 for the ERCOT power region using the
  criteria developed under Subsection (d) or (d-1) when considering
  whether to grant a certificate for a transmission project.
         SECTION 3.  The Public Utility Commission of Texas shall
  adopt any rules necessary to implement the changes in law made by
  Section 37.056(d-1), Utilities Code, as added by this Act, not
  later than September 1, 2026.
         SECTION 4.  The Public Utility Commission of Texas shall
  direct the independent organization certified for the ERCOT power
  region under Section 39.151, Utilities Code, to take any action
  necessary for the implementation of the changes in law made by this
  Act not later than September 1, 2026.
         SECTION 5.  The changes in law made by this Act apply only to
  a proceeding affecting a certificate of public convenience and
  necessity that commences on or after September 1, 2026. A
  proceeding affecting a certificate of public convenience and
  necessity that commenced before that date is governed by the law in
  effect on the date the proceeding is commenced, and that law is
  continued in effect for that purpose.
         SECTION 6.  This Act takes effect September 1, 2025.