|
|
|
A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the location of and light pollution mitigation for wind |
|
turbine generators; authorizing an administrative penalty. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Subchapter A, Chapter 35, Utilities Code, is |
|
amended by adding Sections 35.0023 and 35.0024 to read as follows: |
|
Sec. 35.0023. WIND TURBINE LIGHT POLLUTION MITIGATION. (a) |
|
This section applies only to an electric cooperative, electric |
|
utility, municipally owned utility, power generation company, or |
|
exempt wholesale generator that: |
|
(1) is required by the Federal Aviation Administration |
|
to use aviation obstruction lighting; and |
|
(2) sells at wholesale electric energy produced by a |
|
wind turbine generator. |
|
(b) The commission by rule shall require an electric |
|
cooperative, electric utility, municipally owned utility, power |
|
generation company, or exempt wholesale generator to apply to the |
|
Federal Aviation Administration, or another applicable federal |
|
entity, for authorization to install and operate technology to |
|
mitigate light pollution from the wind turbine generator using a |
|
light mitigation technology system. |
|
(c) The rules adopted under Subsection (b) must require an |
|
electric cooperative, electric utility, municipally owned utility, |
|
power generation company, or exempt wholesale generator that: |
|
(1) installs a wind turbine generator on or after |
|
December 31, 2026, to: |
|
(A) submit an application for approval of light |
|
mitigation technology to the Federal Aviation Administration not |
|
later than 180 days before the commercial operations date for the |
|
wind turbine generator; |
|
(B) install light mitigation technology on all |
|
wind turbine generators not later than 18 months after receiving |
|
approval of the technology from the Federal Aviation |
|
Administration; and |
|
(C) if installation of the light mitigation |
|
technology is delayed due to forces outside of the control of the |
|
cooperative, utility, company, or generator, make a quarterly |
|
report to the commission detailing the reasons for the delay; or |
|
(2) installs a wind turbine generator before December |
|
31, 2026, to: |
|
(A) on repowering or not later than the 180th day |
|
after the execution of a newly signed long-term power purchase |
|
agreement, submit an application for approval of light mitigation |
|
technology to the Federal Aviation Administration; |
|
(B) install light mitigation technology on all |
|
wind turbine generators not later than 18 months after receiving |
|
approval of the technology from the Federal Aviation |
|
Administration; and |
|
(C) if installation of the light mitigation |
|
technology is delayed due to forces outside of the control of the |
|
cooperative, utility, company, or generator, make a quarterly |
|
report to the commission detailing the reasons for the delay. |
|
(d) Subsection (c) applies only to a wind turbine generator |
|
with a commercial operations date that occurs after December 31, |
|
2008. |
|
(e) Notwithstanding Section 15.023(b), the total amount of |
|
an administrative penalty assessed for a violation continuing or |
|
occurring on separate days under this section may not exceed $1 |
|
million. |
|
Sec. 35.0024. WIND TURBINE GENERATION FACILITY |
|
DETERMINATION. (a) Before an electric cooperative, electric |
|
utility, municipally owned utility, power generation company, or |
|
other person required by commission rule to register with the |
|
commission before generating electricity may begin operation of or |
|
expand a wind turbine generation facility, the cooperative, |
|
utility, company, or person must submit documentation to the |
|
commission establishing that: |
|
(1) the Federal Aviation Administration has |
|
determined the facility will not be a hazard to air navigation; and |
|
(2) the Military Aviation and Installation Assurance |
|
Siting Clearinghouse, or its successor agency, has determined that: |
|
(A) the facility will not have an adverse impact |
|
on military operations or readiness; or |
|
(B) a mitigation agreement has been executed to |
|
overcome an adverse impact on military operations or readiness. |
|
(b) The commission may impose an administrative penalty |
|
under Section 15.023 on an electric cooperative or municipally |
|
owned utility that violates Subsection (a). |
|
SECTION 2. Section 35.0024, Utilities Code, as added by |
|
this Act, applies only to a wind turbine generation facility |
|
installed on or after the effective date of this Act. A generation |
|
facility installed before the effective date of this Act is |
|
governed by the law as it existed immediately before that date, and |
|
the law is continued in effect for that purpose. |
|
SECTION 3. This Act takes effect September 1, 2025. |