89R12258 ANG-D
 
  By: Patterson H.B. No. 3244
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to the location of and light pollution mitigation for wind
  turbine generators; authorizing an administrative penalty.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Subchapter A, Chapter 35, Utilities Code, is
  amended by adding Sections 35.0023 and 35.0024 to read as follows:
         Sec. 35.0023.  WIND TURBINE LIGHT POLLUTION MITIGATION. (a)
  This section applies only to an electric cooperative, electric
  utility, municipally owned utility, power generation company, or
  exempt wholesale generator that:
               (1)  is required by the Federal Aviation Administration
  to use aviation obstruction lighting; and
               (2)  sells at wholesale electric energy produced by a
  wind turbine generator.
         (b)  The commission by rule shall require an electric
  cooperative, electric utility, municipally owned utility, power
  generation company, or exempt wholesale generator to apply to the
  Federal Aviation Administration, or another applicable federal
  entity, for authorization to install and operate technology to
  mitigate light pollution from the wind turbine generator using a
  light mitigation technology system.
         (c)  The rules adopted under Subsection (b) must require an
  electric cooperative, electric utility, municipally owned utility,
  power generation company, or exempt wholesale generator that:
               (1)  installs a wind turbine generator on or after
  December 31, 2026, to:
                     (A)  submit an application for approval of light
  mitigation technology to the Federal Aviation Administration not
  later than 180 days before the commercial operations date for the
  wind turbine generator;
                     (B)  install light mitigation technology on all
  wind turbine generators not later than 18 months after receiving
  approval of the technology from the Federal Aviation
  Administration; and
                     (C)  if installation of the light mitigation
  technology is delayed due to forces outside of the control of the
  cooperative, utility, company, or generator, make a quarterly
  report to the commission detailing the reasons for the delay; or
               (2)  installs a wind turbine generator before December
  31, 2026, to:
                     (A)  on repowering or not later than the 180th day
  after the execution of a newly signed long-term power purchase
  agreement, submit an application for approval of light mitigation
  technology to the Federal Aviation Administration;
                     (B)  install light mitigation technology on all
  wind turbine generators not later than 18 months after receiving
  approval of the technology from the Federal Aviation
  Administration; and
                     (C)  if installation of the light mitigation
  technology is delayed due to forces outside of the control of the
  cooperative, utility, company, or generator, make a quarterly
  report to the commission detailing the reasons for the delay.
         (d)  Subsection (c) applies only to a wind turbine generator
  with a commercial operations date that occurs after December 31,
  2008.
         (e)  Notwithstanding Section 15.023(b), the total amount of
  an administrative penalty assessed for a violation continuing or
  occurring on separate days under this section may not exceed $1
  million.
         Sec. 35.0024.  WIND TURBINE GENERATION FACILITY
  DETERMINATION.  (a)  Before an electric cooperative, electric
  utility, municipally owned utility, power generation company, or
  other person required by commission rule to register with the
  commission before generating electricity may begin operation of or
  expand a wind turbine generation facility, the cooperative,
  utility, company, or person must submit documentation to the
  commission establishing that:
               (1)  the Federal Aviation Administration has
  determined the facility will not be a hazard to air navigation; and
               (2)  the Military Aviation and Installation Assurance
  Siting Clearinghouse, or its successor agency, has determined that:
                     (A)  the facility will not have an adverse impact
  on military operations or readiness; or
                     (B)  a mitigation agreement has been executed to
  overcome an adverse impact on military operations or readiness.
         (b)  The commission may impose an administrative penalty
  under Section 15.023 on an electric cooperative or municipally
  owned utility that violates Subsection (a).
         SECTION 2.  Section 35.0024, Utilities Code, as added by
  this Act, applies only to a wind turbine generation facility
  installed on or after the effective date of this Act.  A generation
  facility installed before the effective date of this Act is
  governed by the law as it existed immediately before that date, and
  the law is continued in effect for that purpose.
         SECTION 3.  This Act takes effect September 1, 2025.