A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the use of geothermal energy as a dispatchable |
|
generation resource. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Subchapter A, Chapter 34, Utilities Code, is |
|
amended by adding Section 34.01015 to read as follows: |
|
Sec. 34.01015. APPLICABILITY. For the purposes of this |
|
chapter: |
|
(1) a generating facility is considered to be |
|
dispatchable if the facility's output can be controlled primarily |
|
by forces under human control; and |
|
(2) a geothermal energy generation facility is |
|
considered to be dispatchable. |
|
SECTION 2. Section 34.0104, Utilities Code, is amended by |
|
amending Subsection (a) and adding Subsection (a-1) to read as |
|
follows: |
|
(a) The commission may use money in the fund without further |
|
appropriation to provide loans to finance upgrades to existing |
|
dispatchable electric generating facilities providing power for |
|
the ERCOT power region that result in a net increase of at least 100 |
|
megawatts of capacity for each facility or the construction of |
|
dispatchable electric generating facilities providing power for |
|
the ERCOT power region that each have a generation capacity of at |
|
least 100 megawatts. [For the purposes of this section, a |
|
generating facility is considered to be dispatchable if the |
|
facility's output can be controlled primarily by forces under human |
|
control.] An electric energy storage facility, other than a |
|
geothermal energy conservation well, is not eligible for a loan |
|
under this section. |
|
(a-1) Notwithstanding Subsections (a) and (b)(1), the |
|
commission may use money in the fund, without further |
|
appropriation, to provide loans to finance the construction of |
|
geothermal energy generation facilities and geothermal energy |
|
conservation wells in the ERCOT power region that have a generation |
|
capacity of at least 10 megawatts. |
|
SECTION 3. Sections 34.0105(a) and (c), Utilities Code, are |
|
amended to read as follows: |
|
(a) The commission shall provide, using money available in |
|
the fund for the purpose without further appropriation, a |
|
completion bonus grant for the construction of dispatchable |
|
electric generating facilities in the ERCOT power region. [For the |
|
purposes of this section, a generating facility is considered to be |
|
dispatchable if the facility's output can be controlled primarily |
|
by forces under human control.] An electric energy storage |
|
facility, other than a geothermal energy conservation well, is not |
|
eligible for a grant under this section. |
|
(c) The commission may provide a grant under this section |
|
only for construction of a facility that: |
|
(1) will have a generation capacity of at least 100 |
|
megawatts or at least 10 megawatts for a geothermal energy |
|
generation facility or geothermal energy conservation well; and |
|
(2) does not meet the planning model requirements |
|
necessary to be included in the Capacity Demand and Reserves Report |
|
of the independent organization certified under Section 39.151 for |
|
the ERCOT power region before June 1, 2023. |
|
SECTION 4. Section 39.159(a), Utilities Code, is amended to |
|
read as follows: |
|
(a) For the purposes of this section: |
|
(1)[,] a generation facility is considered to be |
|
dispatchable if the facility's output can be controlled primarily |
|
by forces under human control; and |
|
(2) a geothermal energy generation facility and a |
|
geothermal energy conservation well are considered to be |
|
dispatchable [non-dispatchable if the facility's output is |
|
controlled primarily by forces outside of human control]. |
|
SECTION 5. This Act takes effect September 1, 2025. |