|
|
|
A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the interconnection and operation of large loads. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Subchapter D, Chapter 39, Utilities Code, is |
|
amended by adding Section 39.169 to read as follows: |
|
Sec. 39.169. LARGE LOAD INTERCONNECTION. (a) In this |
|
section: |
|
(1) "Behind-the-meter generation" means a generation |
|
facility on the retail customer's side of the meter capable of |
|
serving the full load requirement of the retail customer. |
|
(2) "Flexible load" means a large load operated by a |
|
retail customer who is obligated by contract or agreement in the |
|
ERCOT market to reduce the load or power the load exclusively with |
|
back-up generation: |
|
(A) at the direction of the independent |
|
organization certified under Section 39.151 for the ERCOT power |
|
region; or |
|
(B) as required to protect the integrity of the |
|
ERCOT grid. |
|
(b) The commission by rule shall establish a program to |
|
provide an expedited process for the interconnection of large |
|
loads. The program must require the interconnecting electric |
|
cooperative, municipally owned utility, or transmission and |
|
distribution utility and the independent organization certified |
|
under Section 39.151 for the ERCOT power region to give priority in |
|
the interconnection queue to a large load for which a retail |
|
customer has received approval for expedited processing over any |
|
other large loads that have not entered into a contractual |
|
agreement with the electric utility, electric cooperative, or |
|
municipally owned utility regarding the provision of electric |
|
service. If applicable, the generation interconnection |
|
application for a generation facility associated with the large |
|
load must be processed in parallel with the large load. |
|
(c) The program must require a large load to qualify for |
|
expedited interconnection processing by bringing in-service, not |
|
later than the 180th day after the interconnection date, |
|
behind-the-meter generation that is: |
|
(1) registered with the independent organization |
|
certified under Section 39.151 for the ERCOT power region; and |
|
(2) capable of serving the full load requirement of |
|
the customer. |
|
(d) As an alternative to the requirements of Subsection (c), |
|
a large load may qualify for expedited interconnection processing, |
|
if the load is a facility with an aggregated peak demand at a single |
|
site of more than 75 megawatts, by: |
|
(1) providing to the interconnecting electric |
|
cooperative, municipally owned utility, or transmission and |
|
distribution utility all data regarding, and posting all required |
|
financial security for, the load; and |
|
(2) being subject to a binding commitment with the |
|
independent organization certified under Section 39.151 for the |
|
ERCOT power region to establish the load as a flexible load for a |
|
minimum period established by the commission, which must be at |
|
least 10 years. |
|
(e) A large load that qualifies for expedited |
|
interconnection processing may choose: |
|
(1) if authorized by the independent organization |
|
certified under Section 39.151 for the ERCOT power region and the |
|
relevant electric cooperative, municipally owned utility, or |
|
transmission and distribution utility, to contract with a vendor |
|
approved by the relevant electric cooperative, municipally owned |
|
utility, or transmission and distribution utility or by the |
|
independent organization to perform all studies required by the |
|
relevant electric cooperative, municipally owned utility, or |
|
transmission and distribution utility before the approval of the |
|
interconnection application; and |
|
(2) if authorized by the relevant electric |
|
cooperative, municipally owned utility, or transmission and |
|
distribution utility: |
|
(A) to procure equipment required for the |
|
interconnection in accordance with technical specifications |
|
provided by the relevant electric cooperative, municipally owned |
|
utility, or transmission and distribution utility; and |
|
(B) to construct interconnection facilities in |
|
accordance with technical and other requirements of the relevant |
|
electric cooperative, municipally owned utility, or transmission |
|
and distribution utility. |
|
(f) The program may provide that studies required by an |
|
electric cooperative, municipally owned utility, or transmission |
|
and distribution utility before the approval of an interconnection |
|
application for a flexible load may evaluate the load as non-firm. |
|
(g) Demand reductions from flexible loads that receive |
|
expedited processing and are removed from the system through the |
|
utilization of behind-the-meter generation during an energy |
|
emergency alert must be counted toward any obligation of the |
|
electric cooperative, municipally owned utility, or transmission |
|
and distribution utility to shed load. |
|
(h) The independent organization certified under Section |
|
39.151 for the ERCOT power region shall consider action taken under |
|
this section as a reliability deployment when calculating any price |
|
adjustments for reliability deployments. |
|
(i) The commission shall establish financial penalties the |
|
commission may impose on an owner or operator of a large load that |
|
is approved for expedited interconnection processing but fails to |
|
reduce the load or power the load with back-up generation as |
|
directed by the independent organization certified under Section |
|
39.151 for the ERCOT power region. |
|
SECTION 2. This Act takes effect September 1, 2025. |