By: Darby H.B. No. 3970
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to the interconnection and operation of large loads.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Subchapter D, Chapter 39, Utilities Code, is
  amended by adding Section 39.169 to read as follows:
         Sec. 39.169.  LARGE LOAD INTERCONNECTION. (a) In this
  section:
               (1)  "Behind-the-meter generation" means a generation
  facility on the retail customer's side of the meter capable of
  serving the full load requirement of the retail customer.
               (2)  "Flexible load" means a large load operated by a
  retail customer who is obligated by contract or agreement in the
  ERCOT market to reduce the load or power the load exclusively with
  back-up generation:
                     (A)  at the direction of the independent
  organization certified under Section 39.151 for the ERCOT power
  region; or
                     (B)  as required to protect the integrity of the
  ERCOT grid.
         (b)  The commission by rule shall establish a program to
  provide an expedited process for the interconnection of large
  loads.  The program must require the interconnecting electric
  cooperative, municipally owned utility, or transmission and
  distribution utility and the independent organization certified
  under Section 39.151 for the ERCOT power region to give priority in
  the interconnection queue to a large load for which a retail
  customer has received approval for expedited processing over any
  other large loads that have not entered into a contractual
  agreement with the electric utility, electric cooperative, or
  municipally owned utility regarding the provision of electric
  service.  If applicable, the generation interconnection
  application for a generation facility associated with the large
  load must be processed in parallel with the large load.
         (c)  The program must require a large load to qualify for
  expedited interconnection processing by bringing in-service, not
  later than the 180th day after the interconnection date,
  behind-the-meter generation that is:
               (1)  registered with the independent organization
  certified under Section 39.151 for the ERCOT power region; and
               (2)  capable of serving the full load requirement of
  the customer.
         (d)  As an alternative to the requirements of Subsection (c),
  a large load may qualify for expedited interconnection processing,
  if the load is a facility with an aggregated peak demand at a single
  site of more than 75 megawatts, by:
               (1)  providing to the interconnecting electric
  cooperative, municipally owned utility, or transmission and
  distribution utility all data regarding, and posting all required
  financial security for, the load; and
               (2)  being subject to a binding commitment with the
  independent organization certified under Section 39.151 for the
  ERCOT power region to establish the load as a flexible load for a
  minimum period established by the commission, which must be at
  least 10 years.
         (e)  A large load that qualifies for expedited
  interconnection processing may choose:
               (1)  if authorized by the independent organization
  certified under Section 39.151 for the ERCOT power region and the
  relevant electric cooperative, municipally owned utility, or
  transmission and distribution utility, to contract with a vendor
  approved by the relevant electric cooperative, municipally owned
  utility, or transmission and distribution utility or by the
  independent organization to perform all studies required by the
  relevant electric cooperative, municipally owned utility, or
  transmission and distribution utility before the approval of the
  interconnection application; and
               (2)  if authorized by the relevant electric
  cooperative, municipally owned utility, or transmission and
  distribution utility:
                     (A)  to procure equipment required for the
  interconnection in accordance with technical specifications
  provided by the relevant electric cooperative, municipally owned
  utility, or transmission and distribution utility; and
                     (B)  to construct interconnection facilities in
  accordance with technical and other requirements of the relevant
  electric cooperative, municipally owned utility, or transmission
  and distribution utility.
         (f)  The program may provide that studies required by an
  electric cooperative, municipally owned utility, or transmission
  and distribution utility before the approval of an interconnection
  application for a flexible load may evaluate the load as non-firm.
         (g)  Demand reductions from flexible loads that receive
  expedited processing and are removed from the system through the
  utilization of behind-the-meter generation during an energy
  emergency alert must be counted toward any obligation of the
  electric cooperative, municipally owned utility, or transmission
  and distribution utility to shed load.
         (h)  The independent organization certified under Section
  39.151 for the ERCOT power region shall consider action taken under
  this section as a reliability deployment when calculating any price
  adjustments for reliability deployments.
         (i)  The commission shall establish financial penalties the
  commission may impose on an owner or operator of a large load that
  is approved for expedited interconnection processing but fails to
  reduce the load or power the load with back-up generation as
  directed by the independent organization certified under Section
  39.151 for the ERCOT power region.
         SECTION 2.  This Act takes effect September 1, 2025.