|
|
|
A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the interconnection of large loads; providing an |
|
administrative penalty. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Subchapter D, Chapter 39, Utilities Code, is |
|
amended by adding Section 39.169 to read as follows: |
|
Sec. 39.169. LARGE LOAD INTERCONNECTION. (a) In this |
|
section: |
|
(1) "Behind-the-meter generation" means a new |
|
generation facility on the retail customer's side of the meter |
|
capable of serving the full load requirement of the retail |
|
customer. |
|
(2) "Flexible load" means a load operated by a retail |
|
customer who is obligated by contract or agreement in the ERCOT |
|
market to reduce the load or power the load exclusively with back-up |
|
generation: |
|
(A) at the direction of the independent |
|
organization certified under Section 39.151 for the ERCOT power |
|
region; or |
|
(B) as required to protect the integrity of the |
|
ERCOT grid. |
|
(b) The commission by rule shall establish a program to |
|
provide an expedited process for the interconnection of large |
|
loads. The program must require the interconnecting electric |
|
cooperative, municipally owned utility, or transmission and |
|
distribution utility and the independent organization certified |
|
under Section 39.151 for the ERCOT power region to give priority in |
|
the interconnection queue to a large load for which a retail |
|
customer has received approval for expedited processing over any |
|
other large loads. If applicable, the generation interconnection |
|
application for the large load's behind-the-meter generation must |
|
be processed in parallel with the large load. |
|
(c) The program must require a large load to qualify for |
|
expedited interconnection processing by bringing in-service, not |
|
later than the 180th day after the interconnection date, |
|
behind-the-meter generation that is: |
|
(1) registered with the independent organization |
|
certified under Section 39.151 for the ERCOT power region; and |
|
(2) capable of serving the full load requirement of |
|
the customer. |
|
(d) As an alternative to the requirements of Subsection (c), |
|
a large load may qualify for expedited interconnection processing |
|
if the load is a facility with an aggregated peak demand at a single |
|
site of more than 75 megawatts by: |
|
(1) providing to the interconnecting entity all data |
|
regarding, and posting all required financial security for, the |
|
load; and |
|
(2) being subject to a contract or agreement with the |
|
independent organization certified under Section 39.151 for the |
|
ERCOT power region to establish the load as a flexible load for a |
|
minimum period established by the commission, which must be at |
|
least 10 years. |
|
(e) A large load that qualifies for expedited |
|
interconnection processing may choose: |
|
(1) if authorized by the independent organization |
|
certified under Section 39.151 for the ERCOT power region and the |
|
relevant electric cooperative, municipally owned utility, or |
|
transmission and distribution utility, to contract with a vendor |
|
approved by the relevant electric cooperative, municipally owned |
|
utility, or transmission and distribution utility or by the |
|
independent organization to perform all studies required by the |
|
relevant electric cooperative, municipally owned utility, or |
|
transmission and distribution utility before the approval of the |
|
interconnection application; and |
|
(2) if authorized by the relevant electric |
|
cooperative, municipally owned utility, or transmission and |
|
distribution utility: |
|
(A) to procure equipment required for the |
|
interconnection in accordance with technical specifications |
|
provided by the relevant electric cooperative, municipally owned |
|
utility, or transmission and distribution utility; and |
|
(B) to construct interconnection facilities in |
|
accordance with technical and other requirements of the relevant |
|
electric cooperative, municipally owned utility, or transmission |
|
and distribution utility. |
|
(f) The program may provide that studies required by an |
|
electric cooperative, municipally owned utility, or transmission |
|
and distribution utility before the approval of an interconnection |
|
application for a flexible load may evaluate the load as non-firm. |
|
(g) Demand reductions from flexible loads that receive |
|
expedited processing and are removed from the system through the |
|
utilization of behind-the-meter generation during an energy |
|
emergency alert must be counted toward any obligation of the |
|
electric cooperative, municipally owned utility, or transmission |
|
and distribution utility to shed load. |
|
(h) The commission shall impose an administrative penalty |
|
on an owner or operator of a large load that is approved for |
|
expedited interconnection processing but does not comply with the |
|
requirements of this section. |
|
SECTION 2. This Act takes effect September 1, 2025. |