89R24294 JXC-F
 
  By: Darby H.B. No. 3970
 
  Substitute the following for H.B. No. 3970:
 
  By:  King C.S.H.B. No. 3970
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to the interconnection of large loads; providing an
  administrative penalty.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Subchapter D, Chapter 39, Utilities Code, is
  amended by adding Section 39.169 to read as follows:
         Sec. 39.169.  LARGE LOAD INTERCONNECTION. (a) In this
  section:
               (1)  "Behind-the-meter generation" means a new
  generation facility on the retail customer's side of the meter
  capable of serving the full load requirement of the retail
  customer.
               (2)  "Flexible load" means a load operated by a retail
  customer who is obligated by contract or agreement in the ERCOT
  market to reduce the load or power the load exclusively with back-up
  generation:
                     (A)  at the direction of the independent
  organization certified under Section 39.151 for the ERCOT power
  region; or
                     (B)  as required to protect the integrity of the
  ERCOT grid.
         (b)  The commission by rule shall establish a program to
  provide an expedited process for the interconnection of large
  loads.  The program must require the interconnecting electric
  cooperative, municipally owned utility, or transmission and
  distribution utility and the independent organization certified
  under Section 39.151 for the ERCOT power region to give priority in
  the interconnection queue to a large load for which a retail
  customer has received approval for expedited processing over any
  other large loads.  If applicable, the generation interconnection
  application for the large load's behind-the-meter generation must
  be processed in parallel with the large load.
         (c)  The program must require a large load to qualify for
  expedited interconnection processing by bringing in-service, not
  later than the 180th day after the interconnection date,
  behind-the-meter generation that is:
               (1)  registered with the independent organization
  certified under Section 39.151 for the ERCOT power region; and
               (2)  capable of serving the full load requirement of
  the customer.
         (d)  As an alternative to the requirements of Subsection (c),
  a large load may qualify for expedited interconnection processing
  if the load is a facility with an aggregated peak demand at a single
  site of more than 75 megawatts by:
               (1)  providing to the interconnecting entity all data
  regarding, and posting all required financial security for, the
  load; and
               (2)  being subject to a contract or agreement with the
  independent organization certified under Section 39.151 for the
  ERCOT power region to establish the load as a flexible load for a
  minimum period established by the commission, which must be at
  least 10 years.
         (e)  A large load that qualifies for expedited
  interconnection processing may choose:
               (1)  if authorized by the independent organization
  certified under Section 39.151 for the ERCOT power region and the
  relevant electric cooperative, municipally owned utility, or
  transmission and distribution utility, to contract with a vendor
  approved by the relevant electric cooperative, municipally owned
  utility, or transmission and distribution utility or by the
  independent organization to perform all studies required by the
  relevant electric cooperative, municipally owned utility, or
  transmission and distribution utility before the approval of the
  interconnection application; and
               (2)  if authorized by the relevant electric
  cooperative, municipally owned utility, or transmission and
  distribution utility:
                     (A)  to procure equipment required for the
  interconnection in accordance with technical specifications
  provided by the relevant electric cooperative, municipally owned
  utility, or transmission and distribution utility; and
                     (B)  to construct interconnection facilities in
  accordance with technical and other requirements of the relevant
  electric cooperative, municipally owned utility, or transmission
  and distribution utility.
         (f)  The program may provide that studies required by an
  electric cooperative, municipally owned utility, or transmission
  and distribution utility before the approval of an interconnection
  application for a flexible load may evaluate the load as non-firm.
         (g)  Demand reductions from flexible loads that receive
  expedited processing and are removed from the system through the
  utilization of behind-the-meter generation during an energy
  emergency alert must be counted toward any obligation of the
  electric cooperative, municipally owned utility, or transmission
  and distribution utility to shed load.
         (h)  The commission shall impose an administrative penalty
  on an owner or operator of a large load that is approved for
  expedited interconnection processing but does not comply with the
  requirements of this section.
         SECTION 2.  This Act takes effect September 1, 2025.