2025S0155-1 02/28/25
 
  By: Darby H.B. No. 3970
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to electricity planning for large loads.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Subchapter D, Chapter 39, Utilities Code, is
  amended by adding Section 39.169 to read as follows:
         Sec. 39.169.  LARGE LOAD INTERCONNECTION; RELIABILITY
  PROGRAM. (a) In this section, "behind-the-meter generation" means
  a new generation facility on the retail customer's side of the
  meter.
         (b)  The commission by rule shall require the independent
  organization certified under Section 39.151 for the ERCOT power
  region to develop and implement an interconnection program to
  provide an expedited interconnection process for operators of large
  loads who agree to cease consuming energy from the power grid
  through deployment of their behind-the-meter generation when
  directed to by the independent organization.  The program must be
  available only to large loads that are a facility at a single site
  with an aggregate peak power demand that exceeds a demand threshold
  established by the independent organization.  The threshold must be
  at least 75 megawatts unless the independent organization
  determines that a lower threshold will better ensure reliability in
  the ERCOT power region.
         (c)  The program must require the independent organization
  certified under Section 39.151 for the ERCOT power region and the
  relevant electric cooperative, municipally owned utility, or
  transmission and distribution utility to give priority to a large
  load in the interconnection queue participating in the program.
         (d)  The program must provide that:
               (1)  an interconnection application for a
  participating large load with behind-the-meter generation that
  agrees to offer the energy generated by the behind-the-meter
  generation to the power grid at times directed by the independent
  organization or reduce its energy consumption from the power grid
  to a minimum level established by the independent organization will
  be given priority over other interconnection applications that are
  pending before the independent organization and the relevant
  electric cooperative, municipally owned utility, or transmission
  and distribution utility, including any applications from other
  participating large loads without behind-the-meter generation;
               (2)  if applicable, the generator interconnection
  application for a participating large load's behind-the-meter
  generation will be processed in parallel with the load
  interconnection application; and
               (3)  an applicant for participation in the program may
  choose:
                     (A)  if authorized by the independent
  organization and the relevant electric cooperative, municipally
  owned utility, or transmission and distribution utility, to
  contract with a vendor approved by the relevant electric
  cooperative, municipally owned utility, or transmission and
  distribution utility or by the independent organization to perform
  all studies required by the relevant electric cooperative,
  municipally owned utility, or transmission and distribution
  utility before the approval of the interconnection application;
                     (B)  to procure equipment required for the
  interconnection in accordance with technical specifications
  provided by the relevant electric cooperative, municipally owned
  utility, or transmission and distribution utility; and
                     (C)  to construct interconnection facilities in
  accordance with technical and other requirements of the relevant
  electric cooperative, municipally owned utility, or transmission
  and distribution utility.
         (e)  The program shall provide that studies required by an
  electric cooperative, municipally owned utility, or transmission
  and distribution utility before the approval of an interconnection
  application for a participating large load may evaluate the load as
  non-firm.
         SECTION 2.  This Act takes effect September 1, 2025.