|
|
A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to electricity planning for large loads. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Subchapter D, Chapter 39, Utilities Code, is |
|
amended by adding Section 39.169 to read as follows: |
|
Sec. 39.169. LARGE LOAD INTERCONNECTION; RELIABILITY |
|
PROGRAM. (a) In this section, "behind-the-meter generation" means |
|
a new generation facility on the retail customer's side of the |
|
meter. |
|
(b) The commission by rule shall require the independent |
|
organization certified under Section 39.151 for the ERCOT power |
|
region to develop and implement an interconnection program to |
|
provide an expedited interconnection process for operators of large |
|
loads who agree to cease consuming energy from the power grid |
|
through deployment of their behind-the-meter generation when |
|
directed to by the independent organization. The program must be |
|
available only to large loads that are a facility at a single site |
|
with an aggregate peak power demand that exceeds a demand threshold |
|
established by the independent organization. The threshold must be |
|
at least 75 megawatts unless the independent organization |
|
determines that a lower threshold will better ensure reliability in |
|
the ERCOT power region. |
|
(c) The program must require the independent organization |
|
certified under Section 39.151 for the ERCOT power region and the |
|
relevant electric cooperative, municipally owned utility, or |
|
transmission and distribution utility to give priority to a large |
|
load in the interconnection queue participating in the program. |
|
(d) The program must provide that: |
|
(1) an interconnection application for a |
|
participating large load with behind-the-meter generation that |
|
agrees to offer the energy generated by the behind-the-meter |
|
generation to the power grid at times directed by the independent |
|
organization or reduce its energy consumption from the power grid |
|
to a minimum level established by the independent organization will |
|
be given priority over other interconnection applications that are |
|
pending before the independent organization and the relevant |
|
electric cooperative, municipally owned utility, or transmission |
|
and distribution utility, including any applications from other |
|
participating large loads without behind-the-meter generation; |
|
(2) if applicable, the generator interconnection |
|
application for a participating large load's behind-the-meter |
|
generation will be processed in parallel with the load |
|
interconnection application; and |
|
(3) an applicant for participation in the program may |
|
choose: |
|
(A) if authorized by the independent |
|
organization and the relevant electric cooperative, municipally |
|
owned utility, or transmission and distribution utility, to |
|
contract with a vendor approved by the relevant electric |
|
cooperative, municipally owned utility, or transmission and |
|
distribution utility or by the independent organization to perform |
|
all studies required by the relevant electric cooperative, |
|
municipally owned utility, or transmission and distribution |
|
utility before the approval of the interconnection application; |
|
(B) to procure equipment required for the |
|
interconnection in accordance with technical specifications |
|
provided by the relevant electric cooperative, municipally owned |
|
utility, or transmission and distribution utility; and |
|
(C) to construct interconnection facilities in |
|
accordance with technical and other requirements of the relevant |
|
electric cooperative, municipally owned utility, or transmission |
|
and distribution utility. |
|
(e) The program shall provide that studies required by an |
|
electric cooperative, municipally owned utility, or transmission |
|
and distribution utility before the approval of an interconnection |
|
application for a participating large load may evaluate the load as |
|
non-firm. |
|
SECTION 2. This Act takes effect September 1, 2025. |