By: Anchía H.B. No. 5200
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to the use of grid enhancing technologies and
  high-performance conductors in the ERCOT power region.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Subchapter E, Chapter 36, Utilities Code, is
  amended by adding Section 36.216 to read as follows:
         Sec. 36.216.  GRID ENHANCING TECHNOLOGIES AND
  HIGH-PERFORMANCE CONDUCTORS. (a) In this section:
               (1)  "Advanced power flow controller" means hardware
  and software used to reroute electric energy from overloaded
  transmission lines to underutilized transmission corridors by
  adjusting circuit impedance.
               (2)  "Dynamic line rating system" means hardware or
  software used to calculate the true capacity of transmission lines
  using real-time and forecasted weather conditions.
               (3)  "Grid enhancing technology" means any hardware or
  software technology that enables enhanced or more efficient
  performance from the electric transmission system, including a
  dynamic line rating system, advanced power flow controller
  technology, dynamic contingency response, or a topology
  optimization system or another technology identified by the
  independent organization certified under Section 39.151 for the
  ERCOT power region.
               (4)  "High-performance conductors" means modern
  conductor technologies, including carbon and composite core
  conductors and carbon and composite superconductors, with greater
  performance characteristics than aluminum-conductor
  steel-reinforced conductors, such as increased capacity, higher
  efficiency, and reduced or no thermal sag.
               (5)  "Topology optimization system" means software
  technology that identifies reconfigurations of the transmission
  grid to reroute electric energy from overloaded lines to
  underutilized corridors.
         (b)  The commission shall ensure that the independent
  organization certified under Section 39.151, Utilities Code, for
  the ERCOT power region considers the technical feasibility and
  cost-effectiveness using of grid enhancing technologies and
  high-performance conductors in its evaluation of economic and
  reliability projects during annual regional transmission planning
  to increase transmission capacity, reduce transmission system
  congestion, increase electric reliability, and reduce the risk of
  wildfires. The independent organization may decline to recommend
  the use of grid enhancing technologies in a particular instance it
  determines that it would not be prudent.
         SECTION 2.  (a) The Public Utility Commission of Texas shall
  adopt any necessary rules required by Section 36.216, Utilities
  Code, as added by this Act, not later than January 1, 2026.
         SECTION 3.  This Act takes effect September 1, 2025.