A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the legislature's goals for electric generation |
|
capacity in this state. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 39.9044, Utilities Code, is amended to |
|
read as follows: |
|
Sec. 39.9044. GOAL FOR DISPATCHABLE GENERATION [NATURAL |
|
GAS]. (a) It is the intent of the legislature that 50 percent of |
|
the megawatts of generating capacity installed in the ERCOT power |
|
region [this state] after January 1, 2026 [2000], be sourced from |
|
dispatchable generation other than battery energy storage [use |
|
natural gas]. [To the extent permitted by law, the commission shall |
|
establish a program to encourage utilities to comply with this |
|
section by using natural gas produced in this state as the |
|
preferential fuel. This section does not apply to generating |
|
capacity for renewable energy technologies.] |
|
(b) The commission shall establish a dispatchable |
|
generation [natural gas energy] credits trading program. Any power |
|
generation company, municipally owned utility, or electric |
|
cooperative that does not satisfy the requirements of Subsection |
|
(a) by directly owning or purchasing rights to dispatchable |
|
generation capacity [using natural gas technologies] shall |
|
purchase sufficient dispatchable generation [natural gas energy] |
|
credits, from sources other than battery energy storage capacity, |
|
to satisfy the requirements of this section [by holding natural gas |
|
energy credits in lieu of capacity from natural gas energy |
|
technologies]. A power generation company that exclusively |
|
operates battery energy storage resources is not required to |
|
purchase dispatchable generation credits under this section. |
|
(c) The [Not later than January 1, 2000, the] commission |
|
shall adopt rules necessary to administer and enforce this section |
|
[and to perform any necessary studies in cooperation with the |
|
Railroad Commission of Texas]. At a minimum, the rules must |
|
[shall]: |
|
(1) describe how the commission will calculate |
|
[establish] the [minimum] annual dispatchable [natural gas] |
|
generation requirement for each power generation company, |
|
municipally owned utility, and electric cooperative operating in |
|
the ERCOT power region [this state] in a manner reasonably |
|
calculated by the commission to produce[, on a statewide basis,] |
|
compliance with the requirement prescribed by Subsection (a); and |
|
(2) specify reasonable performance standards that all |
|
dispatchable generation [natural gas] capacity additions must meet |
|
to count against the requirement prescribed by Subsection (a) and |
|
that: |
|
(A) are designed and implemented [operated] so as |
|
to maximize reliability [the energy output from the capacity |
|
additions in accordance with then-current industry standards and |
|
best industry standards]; and |
|
(B) encourage the development, construction, and |
|
operation of new natural gas energy projects at those sites in the |
|
ERCOT power region [this state] that have the greatest economic |
|
potential for capture and development of this state's |
|
environmentally beneficial natural gas resources. |
|
(d) On or before January 1, 2027, the commission shall |
|
activate the dispatchable generation credits trading program |
|
established by this section if the commission determines that |
|
dispatchable generation may provide less than 55 percent of all new |
|
generating capacity installed in the ERCOT power region after |
|
January 1, 2026. Not later than the 180th day after the date of the |
|
program's activation, the commission by rule shall determine the |
|
conditions for compliance and penalties for noncompliance for each |
|
power generation company, municipally owned utility, and electric |
|
cooperative subject to the program. A power generation company |
|
that exclusively operates battery energy storage resources is not |
|
subject to the program. The commission may adopt rules providing |
|
for alternative compliance payments [The commission, with the |
|
assistance of the Railroad Commission of Texas, shall adopt rules |
|
allowing and encouraging retail electric providers and municipally |
|
owned utilities and electric cooperatives that have adopted |
|
customer choice to market electricity generated using natural gas |
|
produced in this state as environmentally beneficial. The rules |
|
shall allow a provider, municipally owned utility, or cooperative |
|
to: |
|
[(1) emphasize that natural gas produced in this state |
|
is the cleanest-burning fossil fuel; and |
|
[(2) label the electricity generated using natural gas |
|
produced in this state as "green" electricity]. |
|
(e) In this section, "dispatchable generation" ["natural |
|
gas technology"] means generating technologies other than |
|
technologies considered non-dispatchable under Section 39.159(a) |
|
[any technology that exclusively relies on natural gas as a primary |
|
fuel source]. |
|
(f) The independent organization certified under Section |
|
39.151 for the ERCOT power region shall establish a tracking system |
|
to award dispatchable generation credits to new dispatchable |
|
generation facilities that meet eligibility requirements |
|
established by the commission. Each megawatt of installed |
|
dispatchable generation capacity energized after January 1, 2026, |
|
is eligible for one dispatchable generation credit. |
|
(g) For the purposes of this subsection, a compliance |
|
premium is an additional tradable instrument that is equal to one |
|
dispatchable generation credit. The commission shall require the |
|
independent organization certified under Section 39.151 for the |
|
ERCOT power region to award to a nuclear generation facility |
|
energized after January 1, 2026, one compliance premium in addition |
|
to each dispatchable generation credit awarded to the facility. |
|
(h) Not later than September 15 of each year, the |
|
independent organization certified under Section 39.151 for the |
|
ERCOT power region shall file with the commission a report on all |
|
generating facilities energized in the ERCOT power region during |
|
the prior year that includes a calculation of whether the prior |
|
year's installed dispatchable generation capacity is in compliance |
|
with this section. |
|
(i) Not later than January 15 of each year, the commission |
|
shall notify each power generation company, municipally owned |
|
utility, and electric cooperative of the power generation |
|
company's, municipally owned utility's, or electric cooperative's |
|
dispatchable generation credits requirement for the prior year, if |
|
any. |
|
(j) Each power generation company, municipally owned |
|
utility, or electric cooperative shall retire sufficient |
|
dispatchable generation credits to meet the power generation |
|
company's, municipally owned utility's, or electric cooperative's |
|
dispatchable generation credits requirement not later than an |
|
annual deadline established by the commission. |
|
SECTION 2. Section 40.004, Utilities Code, is amended to |
|
read as follows: |
|
Sec. 40.004. JURISDICTION OF COMMISSION. Except as |
|
specifically otherwise provided in this chapter, the commission has |
|
jurisdiction over municipally owned utilities only for the |
|
following purposes: |
|
(1) to regulate wholesale transmission rates and |
|
service, including terms of access, to the extent provided by |
|
Subchapter A, Chapter 35; |
|
(2) to regulate certification of retail service areas |
|
to the extent provided by Chapter 37; |
|
(3) to regulate rates on appeal under Subchapters D |
|
and E, Chapter 33, subject to Section 40.051(c); |
|
(4) to establish a code of conduct as provided by |
|
Section 39.157(e) applicable to anticompetitive activities and to |
|
affiliate activities limited to structurally unbundled affiliates |
|
of municipally owned utilities, subject to Section 40.054; |
|
(5) to establish terms and conditions for open access |
|
to transmission and distribution facilities for municipally owned |
|
utilities providing customer choice, as provided by Section 39.203; |
|
(6) to administer the dispatchable generation |
|
[natural gas energy] credits trading program under Section |
|
39.9044(b); |
|
(7) to require reports of municipally owned utility |
|
operations only to the extent necessary to: |
|
(A) enable the commission to determine the |
|
aggregate load and energy requirements of the state and the |
|
resources available to serve that load; or |
|
(B) enable the commission to determine |
|
information relating to market power as provided by Section 39.155; |
|
and |
|
(8) to evaluate and monitor the cybersecurity |
|
preparedness of a municipally owned utility described by Section |
|
39.1516(a)(3) or (4). |
|
SECTION 3. This Act takes effect September 1, 2025. |