A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the design-build method for certain government |
|
construction projects. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Subchapter G, Chapter 2269, Government Code, is |
|
amended by adding Section 2269.3035 to read as follows: |
|
Sec. 2269.3035. ALTERNATIVE DESIGN-BUILD METHODS FOR WATER |
|
AND WASTEWATER INFRASTRUCTURE. (a) A governmental entity may use |
|
the following methods for the construction, rehabilitation, |
|
alteration, or repair of water or wastewater infrastructure: |
|
(1) a method in which a single fixed price for both |
|
design and construction is established at the time the contract |
|
with the design-build firm is signed by the parties, commonly known |
|
as "fixed price design-build"; or |
|
(2) a method in which the design-build firm is |
|
involved early in the process of developing the design and the |
|
contract includes a stepped payment scheme for design and |
|
construction services, commonly known as "progressive |
|
design-build." |
|
(b) The requirements of this subchapter apply to a method |
|
described by Subsection (a) to the extent practicable. |
|
SECTION 2. Section 2269.352, Government Code, is amended to |
|
read as follows: |
|
Sec. 2269.352. APPLICABILITY. This subchapter applies to a |
|
governmental entity, including [that: |
|
[(1) has a population of more than 100,000 within the |
|
entity's geographic boundary or service area; or |
|
[(2) is] a board of trustees governed by Chapter 54, |
|
Transportation Code. |
|
SECTION 3. Section 2269.353(b), Government Code, is amended |
|
to read as follows: |
|
(b) A contract for a project under this subchapter may cover |
|
only a single integrated project. A governmental entity may not |
|
enter into a contract for aggregated projects at multiple |
|
locations. For purposes of this subsection: |
|
(1) if a metropolitan transit authority created under |
|
Chapter 451, Transportation Code, enters into a contract for a |
|
project involving a linear transit project with multiple stops |
|
along the project route for boarding passengers, created under |
|
Chapter 451, Transportation Code, the linear transit project is a |
|
single integrated project; and |
|
(2) a water or wastewater infrastructure project |
|
[treatment plant], including a desalination plant, that includes |
|
treatment facilities, well fields, pump stations, water storage, |
|
and pipelines, is a single integrated project. |
|
SECTION 4. Subchapter H, Chapter 2269, Government Code, is |
|
amended by adding Section 2269.3535 to read as follows: |
|
Sec. 2269.3535. ALTERNATIVE DESIGN-BUILD PROCEDURES FOR |
|
WATER AND WASTEWATER INFRASTRUCTURE. (a) A governmental entity |
|
may use a design-build method described by Section 2269.3035(a) for |
|
the construction, rehabilitation, alteration, or repair of water or |
|
wastewater infrastructure. |
|
(b) The requirements of this subchapter apply to a method |
|
described by Subsection (a) to the extent practicable. |
|
SECTION 5. This Act takes effect September 1, 2025. |