AN ACT
  relating to load forecasts used in transmission planning for the
  ERCOT power region.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Subchapter Z, Chapter 39, Utilities Code, is
  amended by adding Section 39.920 to read as follows:
         Sec. 39.920.  LOAD FORECASTS USED FOR TRANSMISSION PLANNING
  IN ERCOT. (a)  In this section, "transmission or distribution
  service provider" means a transmission and distribution utility,
  municipally owned utility, or electric cooperative that owns or
  operates facilities used for the transmission or distribution of
  electricity.
         (b)  The commission by rule shall prohibit a transmission or
  distribution service provider from including in a load forecast
  submitted to the independent organization certified under Section
  39.151 for the ERCOT power region for transmission planning any
  projected addition of retail demand of 25 megawatts or more at a
  single point of delivery unless each retail customer associated
  with the addition demonstrates that the customer is reasonably
  likely to take electric service at the level, location, and date
  reflected in the load forecast.  The rules may require the
  demonstration to be made by:
               (1)  evidence of a lease or other arrangement
  demonstrating that the customer has an appropriate legal interest
  in the real property associated with the point of delivery;
               (2)  a customer security deposit to be refunded only if
  the additional demand is energized at the level and location
  indicated in the transmission or distribution service provider's
  load forecast;
               (3)  an attestation from the customer confirming the
  amount, location, and energization date of the additional demand
  reflected in the transmission or distribution service provider's
  load forecast; or
               (4)  another method acceptable to the commission.
         (c)  A transmission or distribution service provider shall
  submit an attestation to the independent organization certified
  under Section 39.151 for the ERCOT power region with each load
  forecast described by Subsection (b) stating that each retail
  customer associated with additional demand described by that
  subsection has made the demonstration required by the rules adopted
  under that subsection.
         (d)  The independent organization certified under Section
  39.151 for the ERCOT power region may not include a projected
  addition of retail demand that is subject to Subsection (b) in a
  transmission planning analysis that is used as a basis for a
  determination of transmission need unless:
               (1)  the transmission or distribution service provider
  seeking to include the demand addition submits the attestation
  required by Subsection (c); and
               (2)  the retail customer and the transmission or
  distribution service provider provide to the commission or the
  independent organization all information requested by the
  commission or independent organization, as applicable, regarding
  the customer's demonstration required under Subsection (b).
         (e)  Competitively sensitive information provided in
  response to a request under Subsection (d)(2) is confidential and
  not subject to disclosure under Chapter 552, Government Code.
         (f)  The independent organization certified under Section
  39.151 for the ERCOT power region may adopt protocols as necessary
  to comply with this section and rules adopted by the commission
  under this section.
         (g)  This section does not limit the authority of the
  independent organization certified under Section 39.151 for the
  ERCOT power region when conducting transmission planning analyses
  to rely on a load forecast created by the independent organization
  or a third-party study of future load considered credible by the
  independent organization.
         SECTION 2.  This Act takes effect September 1, 2025.