89R10526 ANG-D
 
  By: Hall, Sparks S.B. No. 1692
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to a limitation on wind and solar installed generation
  capacity in the ERCOT power region.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 39.1592(a), Utilities Code, is amended
  to read as follows:
         (a)  This section applies only to an electric generation
  facility in the ERCOT power region for which a standard generator
  interconnection agreement is signed on or after September 1, 2025
  [January 1, 2027, that has been in operation for at least one year],
  and that is not a self-generator.
         SECTION 2.  Subchapter D, Chapter 39, Utilities Code, is
  amended by adding Section 39.1596 to read as follows:
         Sec. 39.1596.  LIMITATION ON WIND AND SOLAR GENERATION
  CAPACITY. (a)  This section applies only to an electric generation
  facility that:
               (1)  exclusively relies on an energy source derived
  from wind or the sun; and
               (2)  is subject to a standard generator interconnection
  agreement. 
         (b)  Not later than January 1, 2029, the commission shall
  determine whether the installed generation capacity from the
  electric generation facilities described by Subsection (a) is
  contributing more than 35 percent of the available generation
  capacity for the ERCOT power region at any time.
         (c)  If the commission determines the installed generation
  capacity described by Subsection (b) contributes more than 35
  percent of the available generation capacity for the ERCOT power
  region at any time, the commission shall by rule establish a program
  to require disconnection from the power grid of electric generation
  facilities as provided by this subsection.  The program must:
               (1)  require the disconnection from the power grid of
  only facilities for which a standard generator interconnection
  agreement was signed before September 1, 2025; and 
               (2)  establish a goal of reducing the installed
  generation capacity from facilities for which a standard generator
  interconnection agreement was signed before September 1, 2025, so
  that the installed capacity from all electric generation facilities
  exclusively relying on an energy source derived from wind or the sun
  contributes 35 percent or less of the available generation capacity
  for the ERCOT power region at any time. 
         (d)  After completion of the program required under
  Subsection (c), the commission may allow the installation of new
  generation capacity from an electric generation facility described
  by Subsection (a), regardless of the goal described by Subsection
  (c)(2), if the facility complies with Section 39.1592. 
         SECTION 3.  This Act takes effect immediately if it receives
  a vote of two-thirds of all the members elected to each house, as
  provided by Section 39, Article III, Texas Constitution.  If this
  Act does not receive the vote necessary for immediate effect, this
  Act takes effect September 1, 2025.