A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to a limitation on wind and solar installed generation |
|
capacity in the ERCOT power region. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 39.1592(a), Utilities Code, is amended |
|
to read as follows: |
|
(a) This section applies only to an electric generation |
|
facility in the ERCOT power region for which a standard generator |
|
interconnection agreement is signed on or after September 1, 2025 |
|
[January 1, 2027, that has been in operation for at least one year], |
|
and that is not a self-generator. |
|
SECTION 2. Subchapter D, Chapter 39, Utilities Code, is |
|
amended by adding Section 39.1596 to read as follows: |
|
Sec. 39.1596. LIMITATION ON WIND AND SOLAR GENERATION |
|
CAPACITY. (a) This section applies only to an electric generation |
|
facility that: |
|
(1) exclusively relies on an energy source derived |
|
from wind or the sun; and |
|
(2) is subject to a standard generator interconnection |
|
agreement. |
|
(b) Not later than January 1, 2029, the commission shall |
|
determine whether the installed generation capacity from the |
|
electric generation facilities described by Subsection (a) is |
|
contributing more than 35 percent of the available generation |
|
capacity for the ERCOT power region at any time. |
|
(c) If the commission determines the installed generation |
|
capacity described by Subsection (b) contributes more than 35 |
|
percent of the available generation capacity for the ERCOT power |
|
region at any time, the commission shall by rule establish a program |
|
to require disconnection from the power grid of electric generation |
|
facilities as provided by this subsection. The program must: |
|
(1) require the disconnection from the power grid of |
|
only facilities for which a standard generator interconnection |
|
agreement was signed before September 1, 2025; and |
|
(2) establish a goal of reducing the installed |
|
generation capacity from facilities for which a standard generator |
|
interconnection agreement was signed before September 1, 2025, so |
|
that the installed capacity from all electric generation facilities |
|
exclusively relying on an energy source derived from wind or the sun |
|
contributes 35 percent or less of the available generation capacity |
|
for the ERCOT power region at any time. |
|
(d) After completion of the program required under |
|
Subsection (c), the commission may allow the installation of new |
|
generation capacity from an electric generation facility described |
|
by Subsection (a), regardless of the goal described by Subsection |
|
(c)(2), if the facility complies with Section 39.1592. |
|
SECTION 3. This Act takes effect immediately if it receives |
|
a vote of two-thirds of all the members elected to each house, as |
|
provided by Section 39, Article III, Texas Constitution. If this |
|
Act does not receive the vote necessary for immediate effect, this |
|
Act takes effect September 1, 2025. |