A BILL TO BE ENTITLED
|
|
|
AN ACT
|
|
|
relating to registration and community outreach requirements for |
|
|
large data centers. |
|
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
|
SECTION 1. The Utilities Code is amended by adding Title 7 |
|
|
to read as follows: |
|
|
TITLE 7. DATA CENTERS |
|
|
CHAPTER 401. DATA CENTER REGISTRATION AND COMMUNITY ENGAGEMENT |
|
|
NOTICE REQUIREMENTS |
|
|
SUBCHAPTER A. GENERAL PROVISIONS |
|
|
Sec. 401.001. DEFINITIONS. In this title: |
|
|
(1) "Commission" means the Public Utility Commission |
|
|
of Texas. |
|
|
(2) "Developer" means a person who owns, develops, or |
|
|
proposes to develop a large data center. |
|
|
(3) "Electric cooperative" has the meaning assigned by |
|
|
Section 11.003. |
|
|
(4) "Electric utility" has the meaning assigned by |
|
|
Section 31.002. |
|
|
(5) "Large data center" means a facility or group of |
|
|
facilities on a single parcel or contiguous parcels of land under |
|
|
common ownership or control that: |
|
|
(A) comprises at least 250,000 square feet of |
|
|
space; and |
|
|
(B) is constructed or refurbished primarily to |
|
|
house servers and related equipment for the processing, storage, or |
|
|
distribution of data. |
|
|
(6) "Municipally owned utility" has the meaning |
|
|
assigned by Section 11.003. |
|
|
SUBCHAPTER B. REGISTRATION |
|
|
Sec. 401.051. REGISTRATION. (a) The commission by rule |
|
|
shall: |
|
|
(1) require a developer to register the site of a large |
|
|
data center under this section before construction of the data |
|
|
center begins; and |
|
|
(2) establish a method to ensure compliance with this |
|
|
section. |
|
|
(b) The rules must require the developer, before beginning |
|
|
construction of the large data center, to: |
|
|
(1) notify the community about the construction of the |
|
|
large data center as provided by Section 401.101; |
|
|
(2) hold a community meeting as provided by Section |
|
|
401.102; and |
|
|
(3) submit an affidavit to the commission in |
|
|
accordance with Section 401.104 stating that the developer has |
|
|
complied with the requirements of Subchapter C. |
|
|
SUBCHAPTER C. COMMUNITY OUTREACH REQUIREMENTS |
|
|
Sec. 401.101. NOTIFICATION REQUIREMENTS. (a) Not later |
|
|
than the 60th day before holding a community meeting as required by |
|
|
Section 401.102, a developer shall: |
|
|
(1) send written notice of the proposed construction |
|
|
of the large data center: |
|
|
(A) by first-class mail to each owner of real |
|
|
property located wholly or partly within three miles of the |
|
|
boundary on which the proposed data center will be located, using |
|
|
the most recent certified appraisal roll of the appraisal district |
|
|
in which the property is located; and |
|
|
(B) by first-class mail or direct delivery to |
|
|
each residential address located within three miles of the boundary |
|
|
of the proposed large data center; |
|
|
(2) provide written notice of the proposed |
|
|
construction of the large data center to: |
|
|
(A) the county judge of the county in which the |
|
|
proposed large data center will be located; |
|
|
(B) the county commissioner who represents the |
|
|
county precinct in which the proposed large data center will be |
|
|
located; |
|
|
(C) the mayor of the municipality in which the |
|
|
proposed large data center will be located, if applicable; |
|
|
(D) each member of the legislature who represents |
|
|
the area in which the proposed large data center will be located; |
|
|
and |
|
|
(E) any other political subdivisions in which the |
|
|
proposed large data center will be located; |
|
|
(3) publish notice of the proposed construction of the |
|
|
large data center in a newspaper or news publication of general |
|
|
circulation in the county in which the proposed large data center |
|
|
will be located; |
|
|
(4) post a sign providing notice of the proposed |
|
|
construction of the large data center in a conspicuous location at |
|
|
the site of the proposed data center in a location that is visible |
|
|
from a regularly traveled public road; and |
|
|
(5) post a written notice of the proposed construction |
|
|
of and information regarding the proposed large data center, |
|
|
including information regarding the community meeting, on a |
|
|
publicly available Internet website maintained by or operated on |
|
|
behalf of the developer. |
|
|
(b) Notice provided under this section must include: |
|
|
(1) the developer's name and contact information; |
|
|
(2) the location of the proposed large data center; |
|
|
(3) a description in plain language of the proposed |
|
|
large data center; |
|
|
(4) the anticipated square footage of the proposed |
|
|
large data center; |
|
|
(5) the date, time, and location of the planned |
|
|
community meeting required by Section 401.102; |
|
|
(6) a description of the manner in which a person may |
|
|
submit questions or written comments to the developer regarding the |
|
|
proposed large data center; and |
|
|
(7) the Internet website address at which information |
|
|
regarding the proposed large data center and the community meeting |
|
|
may be found. |
|
|
Sec. 401.102. COMMUNITY MEETING REQUIRED. (a) A developer |
|
|
shall hold at least one public community meeting before beginning |
|
|
construction of a proposed large data center. |
|
|
(b) A community meeting held under this section must be held |
|
|
in the county in which the proposed large data center will be |
|
|
located and at a location reasonably accessible to residents who |
|
|
are entitled to notice under Section 401.101. At the meeting, the |
|
|
developer shall: |
|
|
(1) describe the proposed large data center; and |
|
|
(2) provide members of the public: |
|
|
(A) a reasonable opportunity to ask questions |
|
|
regarding the proposed large data center; and |
|
|
(B) an opportunity to: |
|
|
(i) provide oral comments on the proposed |
|
|
large data center to the developer; and |
|
|
(ii) submit written comments on the |
|
|
proposed large data center to the developer. |
|
|
(c) The developer shall accept written comments on the |
|
|
proposed large data center beginning on the date notice is provided |
|
|
under Section 401.101 and until at least the 10th business day after |
|
|
the date of the community meeting held under this section. |
|
|
(d) A developer of a large data center or a representative |
|
|
of the developer must attend the community meeting held under this |
|
|
section. The developer or the developer's representative must: |
|
|
(1) be knowledgeable regarding the proposed large data |
|
|
center; and |
|
|
(2) make a reasonable effort to respond to questions |
|
|
relevant to the proposed large data center. |
|
|
(e) The developer shall make an audio or video recording of |
|
|
the community meeting held under this section. |
|
|
(f) Not later than the 40th day after the date of the |
|
|
community meeting held under this section, the developer shall |
|
|
publish on a publicly available Internet website maintained by or |
|
|
operated on behalf of the developer: |
|
|
(1) the audio or video recording of the meeting; |
|
|
(2) a copy or a summary of the written comments |
|
|
received by the developer; and |
|
|
(3) a written response provided by the developer |
|
|
addressing each relevant and material issue raised by an oral or |
|
|
written comment. |
|
|
(g) The purpose of a community meeting held under this |
|
|
section is to provide information to the public and allow the public |
|
|
to provide input to the developer. The community meeting is not a |
|
|
governmental meeting subject to the meeting or hearing requirements |
|
|
of the Government Code applicable to meetings held by governmental |
|
|
entities. |
|
|
Sec. 401.103. COSTS. A developer is responsible for all |
|
|
costs required for compliance with this subchapter. |
|
|
Sec. 401.104. AFFIDAVIT OF COMPLIANCE. (a) A developer |
|
|
shall submit to the commission a sworn affidavit that the developer |
|
|
has complied with the notice and community meeting requirements |
|
|
under this subchapter. |
|
|
(b) The commission shall verify that the information in the |
|
|
sworn affidavit is correct and share the affidavit with the |
|
|
electric cooperative, electric utility, or municipally owned |
|
|
utility the developer proposes to receive electric service from at |
|
|
the proposed large data center site. |
|
|
(c) An electric cooperative, electric utility, or |
|
|
municipally owned utility may not interconnect facilities at a site |
|
|
on which a large data center is or will be located before receiving |
|
|
a copy of the developer's affidavit from the commission. |
|
|
SUBCHAPTER D. ENFORCEMENT |
|
|
Sec. 401.152. ENFORCEMENT. For purposes of this chapter, a |
|
|
reference in Chapter 15 to a person includes a developer required to |
|
|
register under this chapter. The commission may use any |
|
|
enforcement mechanism authorized by Chapter 15 against a developer, |
|
|
electric cooperative, electric utility, or municipally owned |
|
|
utility that fails to comply with this chapter. |
|
|
SECTION 2. Title 7, Utilities Code, as added by this Act, |
|
|
applies only to a large data center the construction of which begins |
|
|
on or after the effective date of this Act. |
|
|
SECTION 3. This Act takes effect September 1, 2027. |