A BILL TO BE ENTITLED
|
|
|
AN ACT
|
|
|
relating to the permitting of renewable energy generation |
|
|
facilities; authorizing fees. |
|
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
|
SECTION 1. Subchapter C, Chapter 15, Utilities Code, is |
|
|
amended by adding Section 15.053 to read as follows: |
|
|
Sec. 15.053. COMPLAINT REGARDING RENEWABLE ENERGY |
|
|
GENERATION FACILITIES. (a) An affected person may complain to the |
|
|
commission in writing setting forth an act or omission by an owner |
|
|
or operator of a renewable energy generation facility in violation |
|
|
or claimed violation of Subchapter F, Chapter 35. |
|
|
(b) The commission shall keep for a reasonable period an |
|
|
information file about each complaint filed with the commission |
|
|
relating to an owner or operator of a renewable energy generation |
|
|
facility. |
|
|
(c) The commission, at least quarterly and until final |
|
|
disposition of the written complaint, shall notify the parties to |
|
|
the complaint of the status of the complaint unless the notice would |
|
|
jeopardize an undercover investigation. |
|
|
SECTION 2. Chapter 35, Utilities Code, is amended by adding |
|
|
Subchapter F to read as follows: |
|
|
SUBCHAPTER F. RENEWABLE ENERGY GENERATION FACILITY PERMIT |
|
|
Sec. 35.201. DEFINITIONS; APPLICABILITY. (a) In this |
|
|
subchapter: |
|
|
(1) "Permit holder" means a person who holds a permit |
|
|
issued under this subchapter. |
|
|
(2) "Person" includes an electric cooperative and a |
|
|
municipally owned utility. |
|
|
(3) "Renewable energy generation facility" means: |
|
|
(A) a wind power facility as defined by Section |
|
|
301.0001; |
|
|
(B) a solar power facility as defined by Section |
|
|
302.0001; |
|
|
(C) a battery energy storage facility as defined |
|
|
by Section 303.0001 or another type of electric energy storage |
|
|
facility; or |
|
|
(D) a renewable power facility. |
|
|
(4) "Renewable power facility" means a facility that: |
|
|
(A) generates electric energy using a renewable |
|
|
energy technology, as defined by Section 39.916, other than a |
|
|
technology that relies exclusively on wind or solar energy; and |
|
|
(B) is not an electric energy storage facility. |
|
|
(b) The permit requirements of this subchapter apply to a |
|
|
renewable energy generation facility regardless of whether the |
|
|
facility is the subject of a facility agreement entered into under |
|
|
Chapter 301, 302, or 303. |
|
|
(c) This subchapter applies only to a renewable energy |
|
|
generation facility that is intended to be used to sell energy or |
|
|
ancillary services at wholesale. |
|
|
Sec. 35.202. PERMIT REQUIRED. (a) A person may not |
|
|
interconnect a renewable energy generation facility to a |
|
|
transmission facility unless the person holds a permit to operate a |
|
|
renewable energy generation facility issued by the commission under |
|
|
this subchapter. |
|
|
(b) The commission by rule shall require each permitted |
|
|
renewable energy generation facility to be installed only in a |
|
|
location that: |
|
|
(1) for a solar power facility, is at least: |
|
|
(A) 500 feet from any property line, unless the |
|
|
permit holder has obtained a written waiver from each owner of |
|
|
property located less than 500 feet from the permitted facility; |
|
|
and |
|
|
(B) 500 feet from any habitable structure, unless |
|
|
the permit holder has obtained a written waiver from each owner of |
|
|
the habitable structure; |
|
|
(2) for a wind power facility, is at least twice the |
|
|
height of the wind turbine, including the blades of the turbine, |
|
|
from the property line of each property that borders the property on |
|
|
which the permitted facility is located, unless the permit holder |
|
|
has obtained a written waiver from each owner of property located in |
|
|
the applicable area; and |
|
|
(3) for a battery energy storage facility, is at |
|
|
least: |
|
|
(A) 500 feet from any property line, unless the |
|
|
permit holder has obtained a written waiver from each owner of |
|
|
property located less than 500 feet from the permitted facility; |
|
|
and |
|
|
(B) 500 feet from: |
|
|
(i) public ways; |
|
|
(ii) buildings; |
|
|
(iii) stored combustible materials; |
|
|
(iv) hazardous materials; |
|
|
(v) high-piled stock; and |
|
|
(vi) other exposure hazards not associated |
|
|
with electrical grid infrastructure. |
|
|
(c) The commission by rule shall require: |
|
|
(1) each permitted renewable energy generation |
|
|
facility to be installed only in a location that, in the event of an |
|
|
emergency at the site of the permitted renewable energy generation |
|
|
facility, will not block the only access point to a residential |
|
|
area; or |
|
|
(2) an alternate access point to be constructed for |
|
|
any residential area in which an emergency at the site of the |
|
|
permitted facility could block the only access point to the |
|
|
residential area. |
|
|
(d) A person may apply for a permit under this subchapter by |
|
|
filing with the commission: |
|
|
(1) a description of the proposed location of the |
|
|
renewable energy generation facility; |
|
|
(2) a description of the type of renewable energy |
|
|
generation facility; |
|
|
(3) a statement identifying the fire department, as |
|
|
defined by Section 419.021, Government Code, volunteer fire |
|
|
department, fire marshal, or other first responder entity that may |
|
|
reasonably be expected to be the primary first responder to a fire |
|
|
at the location of the renewable energy generation facility; |
|
|
(4) a statement that the person has provided written |
|
|
notice to the entity identified in Subdivision (3) of the |
|
|
applicant's intent to install a renewable energy generation |
|
|
facility; |
|
|
(5) evidence of insurance coverage sufficient to |
|
|
insure against losses arising from the operation of the renewable |
|
|
energy generation facility; and |
|
|
(6) any other information required by commission rule. |
|
|
(e) When an application for a permit, or an amendment to a |
|
|
permit issued under this section, is filed, the commission shall |
|
|
give notice of the application to the county judge of the county in |
|
|
which all or a majority of the renewable energy generation facility |
|
|
is proposed to be located. The county shall publish the notice in |
|
|
at least three consecutive issues of a newspaper with general |
|
|
circulation in the county. The county shall also publish the notice |
|
|
on the county's Internet website. The county may not remove the |
|
|
notice from its Internet website after publication. |
|
|
(f) The commission may hold one or more public meetings on a |
|
|
permit application in the county in which the renewable energy |
|
|
generation facility is proposed to be located. The commission |
|
|
shall hold a public meeting: |
|
|
(1) on the request of a member of the legislature who |
|
|
represents the area in which the renewable energy generation |
|
|
facility is proposed to be located; or |
|
|
(2) if the commission determines there is substantial |
|
|
public interest in the proposed permit. |
|
|
(g) The commission by order or rule may delegate to the |
|
|
executive director or another commission employee the authority to |
|
|
hold a public meeting under this section. |
|
|
(h) The commission may approve an application for a permit |
|
|
only if the commission finds that: |
|
|
(1) issuance of the permit would not violate state or |
|
|
federal law; and |
|
|
(2) the location of the proposed renewable energy |
|
|
generation facility complies with rules adopted under Subsections |
|
|
(b) and (c). |
|
|
(i) The commission by rule shall adopt a fee to be imposed on |
|
|
each permit applicant to cover costs associated with implementing |
|
|
this section. |
|
|
(j) For purposes of this subchapter: |
|
|
(1) a provision of Subchapter B or E, Chapter 14, that |
|
|
authorizes the commission to regulate a public utility also applies |
|
|
to a person required to obtain a permit under this section, |
|
|
including an electric cooperative or a municipally owned utility; |
|
|
and |
|
|
(2) a reference in Chapter 15 to a person includes a |
|
|
person required to obtain a permit under this section, including an |
|
|
electric cooperative or a municipally owned utility. |
|
|
SECTION 3. As soon as practicable after the effective date |
|
|
of this Act, the Public Utility Commission of Texas shall adopt |
|
|
rules to effectuate the changes in law made by this Act. |
|
|
SECTION 4. This Act takes effect immediately if it receives |
|
|
a vote of two-thirds of all the members elected to each house, as |
|
|
provided by Section 39, Article III, Texas Constitution. If this |
|
|
Act does not receive the vote necessary for immediate effect, this |
|
|
Act takes effect September 1, 2027. |