90R1132 ANG-D
 
  By: Hall S.B. No. 461
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to the removal of certain power facilities operated on
  leased property.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 301.0001, Utilities Code, is amended by
  amending Subdivisions (1) and (1-a) and adding Subdivision (1-b) to
  read as follows:
               (1)  "Commission" means the Texas Commission on
  Environmental Quality.
               (1-a)  "Grantee" means a person who[:
                     [(A)]  leases property from a landowner[; and
                     [(B)  operates a wind power facility on the
  property].
               (1-b) [(1-a)]  "Recycle" means the processing of an
  item to recover a usable product.
         SECTION 2.  Sections 301.0004(a), (c), (e), and (g),
  Utilities Code, are amended to read as follows:
         (a)  A wind power facility agreement must provide that the
  grantee shall obtain and deliver to the commission [landowner]
  evidence of financial assurance payable to the landowner that
  conforms to the requirements of this section to secure the
  performance of the grantee's obligations under Section 301.0003.  
  The [Acceptable forms of] financial assurance may be [include a
  parent company guaranty with a minimum investment grade credit
  rating for the parent company issued by a major domestic credit
  rating agency, a letter of credit,] a bond[,] or another form of
  financial assurance acceptable to the landowner.
         (c)  The agreement must provide that:
               (1)  the estimated cost of removing the wind power
  facilities from the landowner's property, recycling or disposing of
  all the components of the wind power facilities, and restoring the
  property to as near as reasonably possible the condition of the
  property as of the date the agreement begins and the estimated
  salvage value of the wind power facilities must be determined by an
  independent, third-party professional engineer licensed in this
  state;
               (2)  the grantee must deliver to the landowner and the
  commission an updated estimate, prepared by an independent,
  third-party professional engineer licensed in this state, of the
  costs and salvage value described by Subdivision (1) [cost of
  removal and recycling or disposal of the wind power facilities and
  the salvage value] at least once every five years for the remainder
  of the term of the agreement; and
               (3)  the grantee is responsible for ensuring that the
  amount of the financial assurance remains sufficient to cover the
  amount required by Subsection (b), consistent with the estimates
  required by this subsection.
         (e)  The agreement must provide that the grantee shall
  deliver the financial assurance to the commission not later than
  the [earlier of:
               [(1)  the] date on which the wind power facility
  agreement begins [is terminated; or
               [(2)  the 10th anniversary of the commercial operations
  date of the wind power facilities located on the landowner's leased
  property].
         (g)  The grantee may not cancel financial assurance before
  the date the grantee has completed the grantee's obligation to
  remove the grantee's wind power facilities located on the
  landowner's property as required [in the manner provided] by this
  chapter, unless the grantee provides the commission [landowner]
  with replacement financial assurance at the time of or before the
  cancellation.  In the event of a transfer of ownership of the
  grantee's wind power facilities, the financial assurance
  [security] provided by the grantee shall remain in place until the
  date evidence of financial assurance [security] meeting the
  requirements of this chapter is provided to the commission
  [landowner].
         SECTION 3.  Section 302.0001, Utilities Code, is amended by
  amending Subdivisions (1) and (1-a) and adding Subdivision (1-b) to
  read as follows:
               (1)  "Commission" means the Texas Commission on
  Environmental Quality.  
               (1-a) "Grantee" means a person, other than an electric
  utility, as defined by Section 31.002, who[:
                     [(A)]  leases property from a landowner[; and
                     [(B)  operates a solar power facility on the
  property].
               (1-b) [(1-a)] "Recycle" means the processing of an item
  to recover a usable product.
         SECTION 4.  Sections 302.0005(a), (c), (e), and (g),
  Utilities Code, are amended to read as follows:
         (a)  A solar power facility agreement must provide that the
  grantee shall obtain and deliver to the commission [landowner]
  evidence of financial assurance payable to the landowner that
  conforms to the requirements of this section to secure the
  performance of the grantee's obligations under Section 302.0004.  
  The [Acceptable forms of] financial assurance may be [include a
  parent company guaranty with a minimum investment grade credit
  rating for the parent company issued by a major domestic credit
  rating agency, a letter of credit,] a bond[,] or another form of
  financial assurance reasonably acceptable to the landowner.
         (c)  The agreement must provide that:
               (1)  the estimated cost of removing the solar power
  facilities from the landowner's property, recycling or disposing of
  all the components of the solar power facilities, and restoring the
  property to as near as reasonably possible the condition of the
  property as of the date the agreement begins and the estimated
  salvage value of the solar power facilities must be determined by an
  independent, third-party professional engineer licensed in this
  state;
               (2)  the grantee must deliver to the landowner and the
  commission an updated estimate, prepared by an independent,
  third-party professional engineer licensed in this state, of the
  costs and salvage value described by Subdivision (1) [cost of
  removal and recycling or disposal of the solar power facilities and
  the salvage value]:
                     (A)  on or before the 10th anniversary of the
  commercial operations date of the solar power facilities; and
                     (B)  at least once every five years after the
  commercial operations date of the solar power facilities for the
  remainder of the term of the agreement; and
               (3)  the grantee is responsible for ensuring that the
  amount of the financial assurance remains sufficient to cover the
  amount required by Subsection (b), consistent with the estimates
  required by this subsection.
         (e)  The agreement must provide that the grantee shall
  deliver the financial assurance to the commission not later than
  the [earlier of:
               [(1)  the] date on which the solar power facility
  agreement begins [is terminated; or
               [(2)  the 20th anniversary of the commercial operations
  date of the solar power facilities located on the landowner's
  leased property].
         (g)  The grantee may not cancel financial assurance before
  the date the grantee has completed the grantee's obligation to
  remove the grantee's solar power facilities located on the
  landowner's property as required [in the manner provided] by this
  chapter, unless the grantee provides the commission [landowner]
  with replacement financial assurance at the time of or before the
  cancellation.  In the event of a transfer of ownership of the
  grantee's solar power facilities, the financial assurance
  [security] provided by the grantee shall remain in place until the
  date evidence of financial assurance [security] meeting the
  requirements of this chapter is provided to the commission
  [landowner].
         SECTION 5.  Section 303.0001, Utilities Code, is amended by
  adding Subdivision (4-a) to read as follows:
               (4-a)  "Commission" means the Texas Commission on
  Environmental Quality.
         SECTION 6.  Section 303.0005, Utilities Code, is amended by
  amending Subsections (a), (c), (d), (e), (f), and (g) and adding
  Subsection (b-1) to read as follows:
         (a)  A battery energy storage facility agreement must
  provide that the grantee shall obtain and deliver to the commission
  [landowner] evidence of financial assurance payable to the
  landowner that conforms to the requirements of this section to
  secure the performance of the grantee's obligations under Section
  303.0004.  The [Acceptable forms of] financial assurance may be
  [include a parent company guaranty with a minimum investment grade
  credit rating for the parent company issued by a major domestic
  credit rating agency, a letter of credit,] a bond[,] or another form
  of financial assurance reasonably acceptable to the landowner.
         (b-1) In addition to the amount required by Subsection (b),
  the amount of financial assurance must include an amount sufficient
  to compensate the landowner for any damages and restoration in the
  event of a fire, chemical spill or leak, thermal runaway,
  explosion, or any other hazard caused by the failure of the battery
  energy storage facility's system.  As an alternative to including
  this amount in the financial assurance, notwithstanding Subsection
  (f), the grantee may provide an insurance policy for this amount
  that designates the landowner as an additional insured.
         (c)  The agreement must provide that:
               (1)  the estimated cost of removing the battery energy
  storage facilities from the landowner's property, recycling or
  disposing of all the components of the battery energy storage
  facilities, and restoring the property to as near as reasonably
  possible the condition of the property as of the date the agreement
  begins, as described by Section 303.0004, [and] the estimated
  salvage value of the battery energy storage facilities, and the
  estimated costs described by Subsection (b-1) must be determined by
  an independent, third-party professional engineer licensed in this
  state;
               (2)  the grantee must deliver to the landowner and the
  commission the estimated costs and [cost of removal and recycling
  or disposal of the battery energy storage facilities and the]
  salvage value described by Subdivision (1) on or before the 10th
  anniversary of the battery operation date of the grantee's battery
  energy storage resources located on the landowner's property; and
               (3)  the grantee must deliver an updated estimate of
  the costs [cost] and salvage value described by Subdivision (1)
  [(2)] at least once every five years after the initial estimate for
  the remainder of the term of the agreement.
         (d)  The grantee is responsible for the costs of obtaining
  financial assurance described by this section and determining the
  estimated removal, recycling, and disposal costs and salvage value
  and costs described by Subsection (b-1).
         (e)  The agreement must provide that the grantee shall
  deliver financial assurance to the commission not later than the
  [earlier of:
               [(1)  the] date on which the battery energy storage
  facility agreement begins [is terminated; or
               [(2)  the 15th anniversary of the battery operation
  date of the grantee's battery energy storage resources located on
  the landowner's property].
         (f)  The grantee is responsible for ensuring that the amount
  of financial assurance remains sufficient to cover the amount
  required by Subsections [Subsection] (b) and (b-1), consistent with
  the estimates required by this section.
         (g)  The grantee may not cancel financial assurance before
  the date the grantee has completed the grantee's obligation to
  remove the grantee's battery energy storage facilities located on
  the landowner's property as required [in the manner provided] by
  this chapter, unless the grantee provides the commission
  [landowner] with replacement financial assurance at the time of or
  before the cancellation. In the event of a transfer of ownership of
  the grantee's battery energy storage facilities, financial
  assurance provided by the grantee shall remain in place until the
  date evidence of financial assurance meeting the requirements of
  this chapter is provided to the commission [landowner].
         SECTION 7.  Title 6, Utilities Code, is amended by adding
  Chapters 304 and 305 to read as follows:
  CHAPTER 304. ELECTRIC ENERGY STORAGE AND RENEWABLE POWER FACILITY
  AGREEMENTS
         Sec. 304.0001.  DEFINITIONS. In this chapter:
               (1)  "Commercial operations date" means the date on
  which a renewable power facility is approved for participation in
  market operations by a regional transmission organization and does
  not include the generation of electric energy or other operations
  conducted before that date for purposes of maintenance and testing.
               (2)  "Commission" means the Texas Commission on
  Environmental Quality.
               (3)  "Electric energy storage facility agreement"
  means a lease agreement between a grantee and a landowner that
  authorizes the grantee to operate an electric energy storage
  facility on the leased property.
               (4)  "Grantee" means a person who leases property from
  a landowner.
               (5)  "Operations date" means the date on which an
  electric energy storage resource is first used for its intended
  purposes.
               (6)  "Recycle" means the processing of an item to
  recover a usable product.
               (7)  "Renewable power facility" means a facility that:
                     (A)  generates electric energy using a renewable
  energy technology, as defined by Section 39.916, other than a
  technology that relies exclusively on wind or solar energy; and
                     (B)  is not an electric energy storage facility.
               (8)  "Renewable power facility agreement" means a lease
  agreement between a grantee and a landowner that authorizes the
  grantee to operate a renewable power facility on the leased
  property.
         Sec. 304.0002.  APPLICABILITY. (a) This chapter applies
  only to an electric energy storage facility or a renewable power
  facility that is intended to provide energy or ancillary services
  at wholesale for a power grid.
         (b)  This chapter does not apply to an agreement that is
  subject to Chapter 301, 302, or 303.
         Sec. 304.0003.  WAIVER VOID; REMEDIES. (a) A provision of
  an electric energy storage facility agreement or a renewable power
  facility agreement that purports to waive a right or exempt a
  grantee from liability or duty established by this chapter is void.
         (b)  A person who is harmed by a violation of this chapter is
  entitled to appropriate injunctive relief to prevent further
  violation of this chapter.
         (c)  The provisions of this section are not exclusive. The
  remedies provided in this section are in addition to any other
  procedures or remedies provided by law.
         Sec. 304.0004.  REQUIRED AGREEMENT PROVISIONS ON ELECTRIC
  ENERGY STORAGE OR RENEWABLE POWER FACILITY REMOVAL. An electric
  energy storage facility agreement or renewable power facility
  agreement must provide that the grantee is responsible for:
               (1)  removing the grantee's electric energy storage
  facilities or renewable power facilities, as applicable, from the
  landowner's property; and
               (2)  restoring the property to as near as reasonably
  possible the condition of the property as of the date the agreement
  begins.
         Sec. 304.0005.  REQUIRED AGREEMENT PROVISIONS ON FINANCIAL
  ASSURANCE. (a) An electric energy storage facility agreement or a
  renewable power facility agreement must provide that the grantee
  shall obtain and deliver to the commission evidence of financial
  assurance payable to the landowner that conforms to the
  requirements of this section to secure the performance of the
  grantee's obligations under Section 304.0004. The financial
  assurance may be a bond or another form of financial assurance
  reasonably acceptable to the landowner.
         (b)  The amount of the financial assurance must be at least
  equal to the estimated amount by which the cost of removing the
  facilities from the landowner's property, recycling or disposing of
  all the components of the facilities, and restoring the property to
  as near as reasonably possible the condition of the property as of
  the date the agreement begins exceeds the salvage value of the
  facilities, less any portion of the value of the facilities pledged
  to secure outstanding debt.
         (c)  In addition to the amount required by Subsection (b),
  the amount of financial assurance for an electric energy storage
  facility must include an amount sufficient to compensate the
  landowner for any damages and restoration in the event of a fire,
  chemical spill or leak, thermal runaway, explosion, or any other
  hazard caused by the failure of the electric energy storage
  facility's system. As an alternative to including this amount in
  the financial assurance, notwithstanding Subsection (d)(3), the
  grantee may provide an insurance policy for this amount that
  designates the landowner as an additional insured.
         (d)  The agreement must provide that:
               (1)  the estimated cost of removing the facilities from
  the landowner's property, recycling or disposing of all the
  components of the facilities, and restoring the property to as near
  as reasonably possible the condition of the property as of the date
  the agreement begins, the estimated salvage value of the
  facilities, and the estimated costs described by Subsection (c)
  must be determined by an independent, third-party professional
  engineer licensed in this state;
               (2)  the grantee must deliver to the landowner and the
  commission an updated estimate, prepared by an independent,
  third-party professional engineer licensed in this state, of the
  costs and salvage value described by Subdivision (1):
                     (A)  on or before the 10th anniversary of the
  operations date or commercial operations date, as applicable, of
  the facilities; and
                     (B)  at least once every five years after the
  operations date or commercial operations date, as applicable, of
  the facilities for the remainder of the term of the agreement; and
               (3)  the grantee is responsible for ensuring that the
  amount of the financial assurance remains sufficient to cover the
  amount required by Subsections (b) and (c), consistent with the
  estimates required by this subsection.
         (e)  The grantee is responsible for the costs of obtaining
  financial assurance described by this section and costs of
  determining the estimated removal, recycling, and disposal costs
  and salvage value and costs described by Subsection (c).
         (f)  The agreement must provide that the grantee shall
  deliver the financial assurance to the commission not later than
  the date the electric energy storage facility agreement or the
  renewable power facility agreement begins.
         (g)  The grantee may not cancel financial assurance before
  the date the grantee has completed the grantee's obligation to
  remove the grantee's facilities located on the landowner's property
  as required by this chapter, unless the grantee provides the
  commission with replacement financial assurance at the time of or
  before the cancellation. In the event of a transfer of ownership of
  the grantee's facilities, financial assurance provided by the
  grantee shall remain in place until the date evidence of financial
  assurance meeting the requirements of this chapter is provided to
  the commission.
  CHAPTER 305. RELEASE OF FINANCIAL ASSURANCE
         Sec. 305.0001.  DEFINITIONS. In this section:
               (1)  "Commission" means the Texas Commission on
  Environmental Quality.
               (2)  "Grantee" means a person who leases property from
  a landowner.
         Sec. 305.0002.  RELEASE OF FINANCIAL ASSURANCE TO GRANTEE.
  (a)  At any time, a grantee may file an application with the
  commission for the release of all or part of a bond or other
  financial assurance provided to the commission by the grantee for a
  landowner under Chapter 301, 302, 303, or 304.
         (b)  The application must be on a form prescribed by the
  commission and, in addition to other information the commission may
  require, must include the type and the approximate date of removal
  and restoration work performed and a description of the results
  achieved.
         (c)  The grantee shall provide a copy of the application to
  the landowner not later than the 30th day after the date the grantee
  files the application with the commission. 
         (d)  Not later than the 45th day after the date the grantee
  files the application, the commission shall conduct an inspection
  and evaluation of the removal and restoration work performed.
         (e)  The commission may release all or part of the financial
  assurance if the commission determines that the grantee has
  completed all or part of the grantee's obligations under the
  agreement entered into under Section 301.0003, 302.0004, 303.0004,
  or 304.0004, as applicable.
         (f)  If the commission disapproves the application for
  release of the financial assurance, the commission shall notify the
  grantee in writing of the reasons for disapproval and recommend
  corrective actions necessary to secure the release of the financial
  assurance.
         Sec. 305.0003.  FORFEITURE OF FINANCIAL ASSURANCE TO
  LANDOWNER. (a)  A landowner may file an application with the
  commission for the forfeiture of all or part of a bond or other
  financial assurance provided to the commission by a grantee for the
  landowner under this chapter if: 
               (1)  the grantee has not completed the grantee's
  obligations under the agreement entered into under Section
  301.0003, 302.0004, 303.0004, or 304.0004, as applicable; and
               (2)  the facility that is the subject of the agreement
  is no longer being used by the grantee to generate or store energy
  in the manner provided by the agreement.
         (b)  The application must be on a form prescribed by the
  commission.
         (c)  The landowner shall provide a copy of the application to
  the grantee not later than the 30th day after the date the landowner
  files the application with the commission. 
         (d)  Not later than the 45th day after the date the landowner
  files the application, the commission shall conduct an inspection
  and evaluation of the property for which the financial assurance
  was provided.
         (e)  The commission may approve the forfeiture of all or part
  of the financial assurance if the commission determines that:
               (1)  the facility that is the subject of the agreement
  is no longer being used to generate or store energy in the manner
  described by the agreement; and
               (2)  the forfeiture is necessary to compensate the
  landowner for any remaining removal and restoration work the
  grantee was required to but did not complete under the agreement.
         (f)  If the commission disapproves the application for
  forfeiture of the financial assurance, the commission shall notify
  the landowner in writing of the reasons for disapproval.
         Sec. 305.0004.  COMMISSION AUTHORITY. (a)  The commission
  shall notify the Public Utility Commission of Texas if the
  commission requires forfeiture of financial assurance under
  Section 305.0003.  The commission and the Public Utility Commission
  of Texas may not issue to a grantee whose financial assurance was
  forfeited under Section 305.0003 any permit, certificate, or
  registration under other law that authorizes the grantee to operate
  a facility to which Chapter 301, 302, 303, or 304 applies or renew
  any such permit, certificate, or registration.
         (b)  In a suit for receivership, garnishment, or bankruptcy,
  or in any other legal action affecting the assets of a grantee that
  is a party to an agreement subject to Chapter 301, 302, 303, or 304,
  the commission may:
               (1)  inform the appropriate court and parties of the
  commission's interest in obtaining notice of the proceedings; and
               (2)  within the time prescribed by the applicable
  statutes, rules, and court orders, intervene and participate in any
  proceedings that affect a landowner not joined in the suit who is a
  party to the agreement with the grantee.
         SECTION 8.  Section 5.013(a), Water Code, is amended to read
  as follows:
         (a)  The commission has general jurisdiction over:
               (1)  water and water rights including the issuance of
  water rights permits, water rights adjudication, cancellation of
  water rights, and enforcement of water rights;
               (2)  continuing supervision over districts created
  under Article III, Sections 52(b)(1) and (2), and Article XVI,
  Section 59, of the Texas Constitution;
               (3)  the state's water quality program including
  issuance of permits, enforcement of water quality rules, standards,
  orders, and permits, and water quality planning;
               (4)  the determination of the feasibility of certain
  federal projects;
               (5)  the adoption and enforcement of rules and
  performance of other acts relating to the safe construction,
  maintenance, and removal of dams;
               (6)  conduct of the state's hazardous spill prevention
  and control program;
               (7)  the administration of the state's program relating
  to inactive hazardous substance, pollutant, and contaminant
  disposal facilities;
               (8)  the administration of a portion of the state's
  injection well program;
               (9)  the administration of the state's programs
  involving underground water and water wells and drilled and mined
  shafts;
               (10)  the state's responsibilities relating to regional
  waste disposal;
               (11)  the responsibilities assigned to the commission
  by:
                     (A)  Chapters 361, 363, 376, 382, 401, 505, 506,
  and 507, Health and Safety Code; and
                     (B)  Title 6, Utilities Code; and
               (12)  any other areas assigned to the commission by
  this code and other laws of this state.
         SECTION 9.  (a)  The changes in law made by this Act apply
  only to a battery energy storage facility agreement, an electric
  energy storage facility agreement, a renewable power facility
  agreement, a solar power facility agreement, or a wind power
  facility agreement entered into on or after the effective date of
  this Act.  An agreement entered into before the effective date of
  this Act is governed by the law applicable to the agreement on the
  date the agreement was entered into, and that law is continued in
  effect for that purpose.
         (b)  Notwithstanding Subsection (a) of this section, a
  battery energy storage facility, electric energy storage facility,
  renewable power facility, solar power facility, or wind power
  facility that has entered into a battery energy storage facility
  agreement, an electric energy storage facility agreement, a
  renewable power facility agreement, a solar power facility
  agreement, or a wind power facility agreement before the effective
  date of this Act shall deliver the financial assurance required
  under Section 301.0004, 302.0005, or 303.0005, Utilities Code, as
  amended by this Act, or Section 304.0005, Utilities Code, as added
  by this Act, to the Texas Commission on Environmental Quality not
  later than the earlier of:
               (1)  the date on which the agreement is amended; or
               (2)  January 1, 2028.
         SECTION 10.  This Act takes effect immediately if it
  receives a vote of two-thirds of all the members elected to each
  house, as provided by Section 39, Article III, Texas Constitution.  
  If this Act does not receive the vote necessary for immediate
  effect, this Act takes effect September 1, 2027.